Filter by category
Filter by Date
Direction - SA region 11/12/2024
Direction - SA region 11/12/2024
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 11/12/2024.
Intervention pricing does not apply to this AEMO intervention event.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
Update - Foreseeable AEMO intervention in SA region
Update - Foreseeable AEMO intervention in SA region
Refer AEMO Electricity Market Notice 121714
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0830 hrs 11/12/2024.
The foreseeable circumstance requiring the need for intervention is Voltage
AEMO estimates that, in the absence of sufficient market response by 1600 hrs 11/12/2024, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0830 hrs 12/12/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Cancellation - Possible intervention to manage power system security in South Australia (SA) region 11/12/2024
Cancellation - Possible intervention to manage power system security in South Australia (SA) region 11/12/2024
Refer Market Notice 121685
AEMO no longer foresees a possible requirement for intervention to manage power system security in SA region. The advice of possible intervention is cancelled from 1615 hrs 10/12/2024.
Manager NEM Real Time Operations
Update - Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 10 Dec 2024
Refer to MN 121688
In order to maintain the power system in a secure operating state in the QLD region, AEMO has invoked automated constraint set CA_SYD_566A36E5 from 1245 hrs to 1510 hrs.
This constraint set contains equations with the following interconnector on the LHS;
NSW1-QLD1, N-Q_MNSP1
Refer to AEMO Network Outage Scheduler (NOS) for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 10 Dec 2024
In order to maintain the power system in a secure operating state in the QLD region, AEMO has invoked automated constraint set CA_SYD_566A36E5 from 1245 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
NSW1-QLD1, N-Q_MNSP1
Refer to AEMO Network Outage Scheduler (NOS) for further information.
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0830 hrs 11/12/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 08/12/2024
In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA_BRIS_5667C22F from 1600 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
N-Q-MNSP1
Refer to AEMO Network Outage Scheduler (NOS) for further information.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 06/12/2024
Cancellation - AEMO Intervention Event - SA region 06/12/2024
Refer to Market Notice 121524
The AEMO Intervention Event and all associated directions are cancelled from 1630 hrs on 08/12/2024.
Manager NEM Real Time Operations