Filter by category
Filter by Date
Cancellation - AEMO Intervention Event - SA region 26/11/2024
Cancellation - AEMO Intervention Event - SA region 26/11/2024
Refer to Market Notice 121002
The AEMO Intervention Event and all associated directions are cancelled from 1700 hrs on 27/11/2024.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 121096
Direction is cancelled from: 1700 hrs 27/11/2024
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 121031
Direction is cancelled from: 1700 hrs 27/11/2024
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 121048
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1700 hrs 27/11/2024.
The direction update is issued at 1620 hrs 27/11/2024.
Manager NEM Real Time Operations
Direction - SA region 27/11/2024
Direction - SA region 27/11/2024
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 27/11/2024.
Intervention pricing does not apply to this AEMO intervention event.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
[EventId:202411271505_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 27 November 2024 15:05
Issued by Australian Energy Market Operator Ltd at 1505 hrs on 27 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1505 hrs on 27 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 121074
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1600 hrs 27/11/2024
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0830 hrs 28/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1500 hrs 28/11/2024 / further notice.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 121074
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1600 hrs 27/11/2024
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0830 hrs 28/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1430 hrs 28/11/2024 / further notice.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
[EventId:202411271420_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 27 November 2024 14:20
Issued by Australian Energy Market Operator Ltd at 1420 hrs on 27 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 November 2024.
Refer to market notice: 121081
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1420 hrs on 27 November 2024.
This is an AEMO autogenerated Market Notice.