Market Notices

121260RESERVE NOTICE29/11/2024 04:54:05 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 29/11/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 29/11/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1730 hrs

The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 1183 MW

Manager NEM Real Time Operations
     
121138GENERAL NOTICE28/11/2024 09:37:07 AM

Planned outage of the Red Cliffs - Wemen - Kerang 220kV line in the VIC region on 30/11/2024.

AEMO ELECTRICITY MARKET NOTICE

The Red Cliffs - Wemen - Kerang 220kV line in the Victorian (VIC) region is planned to be out of service from 0400 hrs to 1430 hrs on 30/11/2024.

A credible contingency event during this planned outage may require:
- Load shedding in the Victorian outer grid; and/ or
- Market intervention, such as the issuing of directions.

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO Operations
     
121128RESERVE NOTICE27/11/2024 08:03:50 PM

Cancellation of Actual (LOR1) condition in the NSW region - 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 27/11/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121106 is cancelled at 2000 hrs 27/11/2024.

Manager NEM Real Time Operations
     
121106RESERVE NOTICE27/11/2024 04:50:52 PM

Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 27/11/2024

The Actual LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121089 has been updated at 1645 hrs to the following:

The Actual LOR1 condition is forecast to exist until 1900 hrs.

The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 859 MW.

Manager NEM Real Time Operations
     
121089RESERVE NOTICE27/11/2024 02:48:34 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 27/11/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1430 hrs.

The Actual LOR1 condition is forecast to exist until 1630 hrs.

The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 710 MW.

Manager NEM Real Time Operations
     
121011RESERVE NOTICE26/11/2024 08:29:09 PM

Cancellation of Actual (LOR1) condition in the NSW region - 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 26/11/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121009 is cancelled at 2015 hrs 26/11/2024.

Manager NEM Real Time Operations
     
121009RESERVE NOTICE26/11/2024 04:56:18 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 26/11/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs

The capacity reserve requirement is 1450 MW
The minimum capacity reserve available is 886 MW

Manager NEM Real Time Operations
     
121008POWER SYSTEM EVENTS26/11/2024 04:55:00 PM

Non-credible contingency event - NSW region - 26/11/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - NSW region - 26/11/2024

At 1637 hrs Uranquinty Unit 12 tripped and at 1639 hrs Uranquinty Units 11 and 13 tripped.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
     
120897RECALL GEN CAPACITY25/11/2024 08:40:06 AM

Request for Generator Recall Information for the period 27/11/2024 for Region QLD

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 120895.

Please provide Generator Recall Information for the period from 27/11/2024, by 1500 hrs on 25/11/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf


AEMO Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm