Filter by category
Filter by Date
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 28/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121066 is cancelled at 1530 hrs 27/11/2024.
Manager NEM Real Time Operations
STPASA - Cancellation of Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 29/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120955 is cancelled at 1400 hrs 27/11/2024.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 03/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period[s]:
From 1530 hrs to 1900 hrs 03/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 963 MW.
AEMO Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 28/11/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 121064 has been updated at 1430 hrs to the following:
[1.] From 1700 hrs 28/11/2024 to 1900 hrs 28/11/2024.
The forecast capacity reserve requirement is 1250 MW.
The minimum capacity reserve available is 755 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 28/11/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 121062 is cancelled at 1400 hrs 27/11/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 27/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121049 has been updated at 1420 hrs to the following:
[1.] From 1600 hrs 27/11/2024 to 1830 hrs 27/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 509 MW.
AEMO is seeking a market response.
AEMO estimates the latest time at which it would need to intervene through an AEMO intervention event is 1330 hrs on 27/11/2024.
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: VIC1
Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV
Duration: 27/11/2024 13:30 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Yallourn - Rowville 7 220 kV line and Yallourn - Rowville 8 220 kV line in VIC1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: VIC1
Lines: Yallourn - Rowville 7 220 kV and Yallourn - Rowville 8 220 kV
Duration: 27/11/2024 13:13 until further notice
Constraint set(s) invoked:
V-ROYP78_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 28/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1430 hrs 28/11/2024 to 1500 hrs 28/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1226 MW.
[2.] From 1600 hrs 28/11/2024 to 1700 hrs 28/11/2024.
The forecast capacity reserve requirement is 1576 MW.
The minimum capacity reserve available is 1147 MW.
[3.] From 1900 hrs 28/11/2024 to 1930 hrs 28/11/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1154 MW.
Manager NEM Real Time Operations