Filter by category
Filter by Date
NON-CONFORMANCE Region NSW1 Thursday, 7 November 2024
NON-CONFORMANCE NSW1 Region Thursday, 7 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 07/11/2024 09:00 to 07/11/2024 10:45
Amount: -50 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the QLD region - 04/11/2024
Cancellation of Actual (LOR1) condition in the QLD region - 04/11/2024
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.119882 is cancelled at 1900 hrs 04/11/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 04/11/2024
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 04/11/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 1135 MW
The minimum capacity reserve available is 875 MW
Manager NEM Real Time Operations
CHG0099569 | Production | Maintenance on Gas B2B Hub databases
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Gas Hub
Change Title: Maintenance on Gas B2B Hub databases
Change Start Date & Time: 17/11/2024 10:00:00 AEST
Change End Date & Time: 17/11/2024 10:30:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: The following impacts are expected during this maintenance:
- Brief 5 to 10 seconds loss of connectivity to the Gas B2B Hub and all ebXML gateways (AEMOMIBB, AGNLGWY, LVI & VENCORP) during the outage window.
- Users are not required to take any action due to this change.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
Cancellation of Actual (LOR1) condition in the QLD region - 31/10/2024
Cancellation of Actual (LOR1) condition in the QLD region - 31/10/2024
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.119713 is cancelled at 1839 hrs 31/10/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 31/10/2024
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 31/10/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs
The forecast capacity reserve requirement is 1298 MW.
The minimum capacity reserve available is 1178 MW.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 31 October 2024
NON-CONFORMANCE Region NSW1 Thursday, 31 October 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:.
Unit: MP1
Duration: 31/10/2024 13:25 to 31/10/2024 13:30
Amount: -52 MW
Constraint: NC-N_MP1
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 31 October 2024
NON-CONFORMANCE QLD1 Region Thursday, 31 October 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 31/10/2024 12:50 to 31/10/2024 13:05
Amount: 24 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Monday, 28 October 2024
NON-CONFORMANCE SA1 Region Monday, 28 October 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: TB2BG1, TB2BL1
Aggregate Dispatch Group: TB2HYB_ADG1
Duration: 28/10/2024 12:05 to 28/10/2024 12:55
Amount: 39 MW
Constraint: NC-S_TB2HYB_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations