Filter by category
Filter by Date
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 18/11/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 18/11/2024 to 1930 hrs 18/11/2024.
The forecast capacity reserve requirement is 867MW.
The minimum capacity reserve available is 484 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120465 is cancelled at 2320 hrs
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17/11/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1630 hrs 17/11/2024 to 1700 hrs 17/11/2024.
The forecast capacity reserve requirement is 1221 MW.
The minimum capacity reserve available is 1163 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 08/11/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120120 is cancelled at 2345 hrs 07/11/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 08/11/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1800 hrs 08/11/2024 to 1900 hrs 08/11/2024.
The forecast capacity reserve requirement is 727 MW.
The minimum capacity reserve available is 694 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 8/11/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120084 is cancelled at 1315 hrs 08/11/2024
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 08/11/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1530 hrs 08/11/2024 to 1600 hrs 08/11/2024.
The forecast capacity reserve requirement is 776 MW.
The minimum capacity reserve available is 735 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 08/11/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120059 is cancelled at 1100 hrs 07/11/2024.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 07/11/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120061 is cancelled at 1145hrs 07/11/2024.
Manager NEM Real Time Operations