Market Notices

121949RESERVE NOTICE15/12/2024 12:56:53 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1700 hrs 16/12/2024 to 1900 hrs 16/12/2024.
The forecast capacity reserve requirement is 1350 MW.
The minimum capacity reserve available is 1202 MW.


Manager NEM Real Time Operations
     
121943SETTLEMENTS RESIDUE15/12/2024 12:31:50 PM

[EventId:202412151230_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 15 December 2024 12:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1230 hrs on 15 December 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 December 2024.

Refer to market notice: 121938

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1230 hrs on 15 December 2024.

This is an AEMO autogenerated Market Notice.
     
121939RESERVE NOTICE15/12/2024 09:19:13 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121927 is cancelled at 0900 hrs 15/12/2024.

AEMO Operations
     
121938SETTLEMENTS RESIDUE15/12/2024 08:20:34 AM

[EventId:202412150820_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 15 December 2024 08:20

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0820 hrs on 15 December 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 December 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0820 hrs on 15 December 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
121937RESERVE NOTICE15/12/2024 04:41:26 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121926 has been updated at 0420 hrs 15/12/2024 to the following:

From 1530 hrs 17/12/2024 to 2100 hrs 17/12/2024.
The forecast capacity reserve requirement is 1045 MW.
The minimum capacity reserve available is 528 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
121927RESERVE NOTICE14/12/2024 07:28:57 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121892 has been updated at 1920 hrs 14/12/2024 to the following:

From 1630 hrs 16/12/2024 to 1830 hrs 16/12/2024.
The forecast capacity reserve requirement is 1001 MW.
The minimum capacity reserve available is 710 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
121926RESERVE NOTICE14/12/2024 07:27:48 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121893 has been updated at 1920 hrs 14/12/2024 to the following:

From 1500 hrs 17/12/2024 to 2000 hrs 17/12/2024.
The forecast capacity reserve requirement is 1115 MW.
The minimum capacity reserve available is 318 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
121918PRICES UNCHANGED14/12/2024 05:26:55 PM

[EventId:202412141700_confirmed] Prices for interval 14-Dec-2024 17:00 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1720 hrs on 14 December 2024

PRICES ARE NOW CONFIRMED for trading interval 14-Dec-2024 17:00.

In accordance with Market Notice 121906 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
121917PRICES UNCHANGED14/12/2024 05:25:23 PM

[EventId:202412141720_confirmed] Prices for interval 14-Dec-2024 17:20 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1720 hrs on 14 December 2024

PRICES ARE NOW CONFIRMED for trading interval 14-Dec-2024 17:20.

In accordance with Market Notice 121912 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     