Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 1100 hrs 30/11/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 27/11/2024
Cancellation - AEMO Intervention Event - SA region 27/11/2024
Refer to Market Notice 121094
The AEMO Intervention Event and all associated directions are cancelled from 1500 hrs on 28/11/2024.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 121091
Direction is cancelled from: 1500 hrs 28/11/2024
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 121090
Direction is cancelled from: 1430 hrs 28/11/2024
Manager NEM Real Time Operations
Cancellation - Inter-regional transfer limit variation - to manage Power System Security in NSW region - 28/11/2024
Refer AEMO Electricity Market Notice 121142
Constraint set I-QN_1000 was invoked from 0955 hrs until 1230 hrs 28/11/2024.
This constraint set contains equations with the following interconnector on the LHS;
NSW1-QLD1
Manager NEM Real Time Operations
Inter-regional transfer limit variation - to manage Power System Security in NSW region - 28/11/2024
In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked the following constraint set I-QN_1000 from 0955 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
NSW1-QLD1
Manager NEM Real Time Operations
Planned outage of the Red Cliffs - Wemen - Kerang 220kV line in the VIC region on 30/11/2024.
The Red Cliffs - Wemen - Kerang 220kV line in the Victorian (VIC) region is planned to be out of service from 0400 hrs to 1430 hrs on 30/11/2024.
A credible contingency event during this planned outage may require:
- Load shedding in the Victorian outer grid; and/ or
- Market intervention, such as the issuing of directions.
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO Operations
End of RERT Dispatch - 27/11/2024 and End of intervention event
End of Reliability and Emergency Reserve Trader (RERT) dispatch for - NSW1 Region - 27/11/2024 and end of AEMO Intervention Event.
Refer AEMO Electricity Market Notices 121102
Activation of reserve contract(s) has ended.
The reserve contract(s) were activated from 15:45 hrs 27/11/2024 to 16:45 hrs 27/11/2024
The AEMO Intervention Event ended from 16:45 hrs 27/11/2024
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - NSW region 27/11/2024
Cancellation - AEMO Intervention Event - NSW region 27/11/2024
Refer to Market Notice 121070
The AEMO Intervention Event and all associated directions are cancelled from 1645 hrs on 27/11/2024.