Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 120722
Direction is cancelled from: 1330 hrs 21/11/2024
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 26/11/2024
AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1430 hrs to 1830 hrs 26/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 269 MW at 1700 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 26/11/2024
The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 120725 is cancelled at 2200 hrs 20/11/2024.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 26/11/2024
AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1530 hrs to 1900 hrs 26/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 12 MW at 1730 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
Network Augmentation Commissioned - QLD Region - 21/11/2024
Network Augmentation Commissioned - QLD Region - 21/11/2024
Commissioned:
Belmont No.2 275 kV 150 MVar reactor
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 120680
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1500 hrs 21/11/2024.
The direction update is issued at 1630 hrs 20/11/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 120679
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1330 hrs 21/11/2024.
The direction update is issued at 1630 hrs 20/11/2024.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 26/11/2024
The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 120702 is cancelled at 1300 hrs 20/11/2024.
AEMO Operations
Project Energy Connect (PEC-1) testing 21st November 2024 0600-0900 for flows in both directions
Refer to market notice 120307
There is an opportunity for testing Project Energy Connect (PEC-1) for flows in both directions up to 50 MW on 21st November from 06:00hrs to 09:00hrs
This test includes includes a fast runback of Murraylink.
Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.
Ben Blake
AEMO Operations