121376INTER-REGIONAL TRANSFER02/12/2024 01:56:02 PM

Inter-Regional Transfer limit variation - Murraylink control unavailable (VIC Region)

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Murraylink control unavailable (VIC Region)

AEMO has been notified that the controls to vary Murraylink output are unavailable until further notice.

Constraint set I-CTRL_ISSUE_ML invoked from 1350 hrs.

The constraint set contains equations with the following interconnector on the LHS:

V-S-MNSP1


Manager NEM Real Time Operations
     
121354RESERVE NOTICE02/12/2024 05:02:59 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 02/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121349 is cancelled at 0430 hrs 02/12/2024.

Manager NEM Real Time Operations
     
121349RESERVE NOTICE02/12/2024 01:53:38 AM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 02/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1800 hrs 02/12/2024 to 1830 hrs 02/12/2024.
The forecast capacity reserve requirement is 935 MW.
The minimum capacity reserve available is 876 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
121309RESERVE NOTICE01/12/2024 10:44:51 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 02/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121302 has been updated at 1040 hrs 01/12/2024 to the following:

[1.] From 1630 hrs 02/12/2024 to 1700 hrs 02/12/2024.
The forecast capacity reserve requirement is 968 MW.
The minimum capacity reserve available is 732 MW.

[2.] From 1730 hrs 02/12/2024 to 1830 hrs 02/12/2024.
The forecast capacity reserve requirement is 978 MW.
The minimum capacity reserve available is 833 MW.

AEMO is seeking a market response.


AEMO Operations
     
121306RESERVE NOTICE01/12/2024 09:10:42 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 02/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121302 has been updated at 0900 hrs 01/12/2024 to the following:

[1.] From 1600 hrs 02/12/2024 to 1900 hrs 02/12/2024.
The forecast capacity reserve requirement is 1097 MW.
The minimum capacity reserve available is 762 MW.

AEMO is seeking a market response.


AEMO Operations
     
121302RESERVE NOTICE30/11/2024 08:51:11 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 02/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

[1.] From 1700 hrs 02/12/2024 to 1730 hrs 02/12/2024.
The forecast capacity reserve requirement is 1330 MW.
The minimum capacity reserve available is 1071 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
121286INTER-REGIONAL TRANSFER30/11/2024 11:36:18 AM

Inter-regional transfer limit variation - Red Cliffs - Wemen 220 kV line - VIC region - 30/11/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Red Cliffs - Wemen 220 kV line - VIC region - 30/11/2024

A planned outage of Red Cliffs - Wemen 220 kV line in the VIC region was scheduled from 0400 hrs 30/11/2024 to 1430 hrs 30/11/2024.

The outage has been completed and Red Cliffs - Wemen 220 kV line returned to service at 1120 hrs 30/11/2024

Constraint set(s) revoked: V-KG_WE_RC

Manager NEM Real Time Operations
     
121263RESERVE NOTICE29/11/2024 06:17:41 PM

Cancellation of Actual (LOR1) condition in the NSW region - 29/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 29/11/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121262 is cancelled at 1815 hrs 29/11/2024.

Manager NEM Real Time Operations
     
121262RESERVE NOTICE29/11/2024 05:43:53 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 29/11/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 29/11/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs

The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 1301 MW

Manager NEM Real Time Operations
     