PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 27/11/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 121029 has been updated at 1000 hrs to the following:
[1.] From 1730 hrs 27/11/2024 to 1830 hrs 27/11/2024.
The forecast capacity reserve requirement is 1258 MW.
The minimum capacity reserve available is 1166 MW.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Wednesday, 27 November 2024
NON-CONFORMANCE QLD1 Region Wednesday, 27 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 27/11/2024 09:45 to 27/11/2024 10:25
Amount: 36 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Wednesday, 27 November 2024
NON-CONFORMANCE QLD1 Region Wednesday, 27 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 27/11/2024 09:55 to 27/11/2024 10:25
Amount: -17 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 27/11/2024
The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 121021 has been updated at 1000 hrs to the following:
[1.] From 1530 hrs 27/11/2024 to 1700 hrs 27/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 87 MW at 1530 hrs.
AEMO is seeking a market response.
AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 1330 hrs.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 27/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1730 hrs 27/11/2024 to 1830 hrs 27/11/2024.
The forecast capacity reserve requirement is 1263 MW.
The minimum capacity reserve available is 919 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 27/11/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 120973 is cancelled at 0845 hrs 27/11/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 27/11/2024
AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1530 hrs 27/11/2024 to 1700 hrs 27/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 84 MW at approximately 1530 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 27/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120975 has been updated at 0115 hrs to the following:
[1.] From 1400 hrs 27/11/2024 to 1430 hrs 27/11/2024.
The forecast capacity reserve requirement is 1360 MW.
The minimum capacity reserve available is 1052 MW.
[2.] From 1900 hrs 27/11/2024 to 2000 hrs 27/11/2024.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 973 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120981 has been updated at 1550 hrs to the following:
[1.] From 1630 hrs 26/11/2024 to 1930 hrs 26/11/2024.
The forecast capacity reserve requirement is 1380 MW.
The minimum capacity reserve available is 989 MW.
Manager NEM Real Time Operations