Filter by category
Filter by Date
Cancellation of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: NSW1
Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV
Cancellation time: 06/12/2024 20:14
Constraint set(s) revoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1
Refer AEMO Electricity Market Notice 121501
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: NSW1
Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV
Duration: 06/12/2024 20:08 until further notice
Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: NSW1
Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV
Cancellation time: 06/12/2024 18:34
Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
Refer AEMO Electricity Market Notice 121522
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202412061820_review] Prices for interval 06-Dec-2024 18:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1815 hrs on 6 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Dec-2024 18:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412061815_review] Prices for interval 06-Dec-2024 18:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1810 hrs on 6 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Dec-2024 18:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412061810_review] Prices for interval 06-Dec-2024 18:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1805 hrs on 6 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Dec-2024 18:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412061805_review] Prices for interval 06-Dec-2024 18:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 6 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Dec-2024 18:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412061800_review] Prices for interval 06-Dec-2024 18:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1755 hrs on 6 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Dec-2024 18:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412061755_review] Prices for interval 06-Dec-2024 17:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1750 hrs on 6 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Dec-2024 17:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.