Market Notices

117105NON-CONFORMANCE23/06/2024 12:55:20 PM

NON-CONFORMANCE Region QLD1 Sunday, 23 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 23 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 23/06/2024 12:15 to 23/06/2024 12:55
Amount: -29 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
117102NON-CONFORMANCE22/06/2024 09:05:13 PM

NON-CONFORMANCE Region QLD1 Saturday, 22 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 22 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: TARONG#2
Duration: 22/06/2024 20:10 to 22/06/2024 21:05
Amount: -18 MW
Constraint: NC-Q_TARONG#2

Auto-generated on behalf of Manager NEM Real Time Operations
117092NON-CONFORMANCE21/06/2024 12:05:15 PM

NON-CONFORMANCE Region QLD1 Friday, 21 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 21 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 21/06/2024 11:25 to 21/06/2024 12:05
Amount: 39 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
117078INTER-REGIONAL TRANSFER19/06/2024 05:27:58 PM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No 1 Leg of Directlink .

The following constraint set was invoked at 1725 hrs 19/06/2024

N-X_MBTE_2

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
117053INTER-REGIONAL TRANSFER18/06/2024 03:19:21 PM

Inter-regional transfer limit variation - Collector Wind Farm to Yass 3L 330kV line - NSW region - 18/06/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Collector Wind Farm to Yass 3L 330kV line - NSW region - 18/06/2024

A planned outage of Collector Wind Farm to Yass 3L 330kV line in the NSW region was scheduled from 0600 hrs 03/04/2024 to 1500 hrs 08/07/2024.

The outage has been completed and Collector Wind Farm to Yass 3L 330kV line returned to service at 1515 hrs 18/06/2024

Constraint set revoked: N-CTYS_3L_WG_CLOSE

Manager NEM Real Time Operations
117026NON-CONFORMANCE17/06/2024 05:25:12 AM

NON-CONFORMANCE Region QLD1 Monday, 17 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 17 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 17/06/2024 04:30 to 17/06/2024 05:25
Amount: -51 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
116940NON-CONFORMANCE11/06/2024 02:25:21 PM

NON-CONFORMANCE Region QLD1 Tuesday, 11 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 11 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 11/06/2024 12:45 to 11/06/2024 14:25
Amount: -23 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
116932NON-CONFORMANCE11/06/2024 12:05:16 PM

NON-CONFORMANCE Region QLD1 Tuesday, 11 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 11 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 11/06/2024 11:15 to 11/06/2024 12:05
Amount: -21 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
116927NON-CONFORMANCE10/06/2024 11:40:17 PM

NON-CONFORMANCE Region QLD1 Monday, 10 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 10 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 10/06/2024 23:35 to 10/06/2024 23:40
Amount: 34 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations