Filter by category
Filter by Date
CHG0090631 | Production | Planned Maintenance to Norwest Internet firewall.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Internet Access
Change Title: Planned Maintenance to Norwest Internet firewall.
Change Start Date & Time: 18/06/2024 20:00:49 AEST
Change End Date & Time: 18/06/2024 23:30:49 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage:
IPWAN Participants - Nil
Lan-2-Lan VPN Participants (IPSEC) - Nil
B2B VPN - May experience a short 5-10 second drop of VPN tunnel connectivity to Norwest DC.
Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO QLD datacenter termination point prior to this scheduled outage.
SSL VPN Participants: Nil
GASHUB: Nil
Other Impacts will have been communicated in advance.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
Planned outage of the Rowville - South Morang 500 kV line in the VIC region on 20/06/2024.
The Rowville - South Morang 500 kV line in the Victoria (VIC) region is planned to be out of service from 1400 hrs to 1630 hrs on 20/06/2024.
A credible contingency event during this planned outage could cause:
- A large reduction in generation in VIC; and/ or
- Restrict power transfer across the VIC - South Australia (SA) interconnector (Heywood interconnector).
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO Operations
QNI Minor testing (Qld to NSW) 19th June 2024
Refer to market notice 117027
There is an opportunity for testing QNI Minor for flows from Qld to NSW up to 1300 MW on Wednesday 19th June 2024 from 0700 to 1000hrs.
This test includes a trip and reclose of a line in northern NSW.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade
Ben Blake
AEMO Operations
CHG0090782 | Production | Planned Outage for the Gas Short Term Trading Market Systems Production.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Short Term Trading Market
Change Title: Planned Outage for the Gas Short Term Trading Market Systems Production.
Change Start Date & Time: 26/06/2024 09:00:00 AEST
Change End Date & Time: 26/06/2024 22:00:00 AEST
Outage Start Date & Time: 26/06/2024 18:30:00 AEST
Outage End Date & Time: 26/06/2024 21:00:00 AEST
Environment: Production
Participant Impact and Requirements: Gas Short Term Trading Market (STTM) services including SWEX and MIS, SPI and SBS will not be available during the outage window in Production.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0090106 | Cancelled | Production | Identity Service Site Transfer
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Identity Service (IDS)
Change Title: Identity Service Site Transfer
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
CHG0089794 | Cancelled | Production | EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Electricity Market Management System
Change Title: EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
CHG0090550 | Cancelled | Production | Maintenance activities to be performed on the Gas Short Term Trading Market Systems Production.
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Gas FRC - CATS
Change Title: Maintenance activities to be performed on the Gas Short Term Trading Market Systems Production.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
CHG0089836 | Completed | Pre-Production | Renewal and update of AEMO's FBS-Test-Hub.aemo.com.au server certificate.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Gas Hub
Change Title: Renewal and update of AEMO's FBS-Test-Hub.aemo.com.au server certificate.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
QNI Minor testing (Qld to NSW) 17th June 2024
Refer to market notice 114742
There is an opportunity for testing QNI Minor for flows from Qld to NSW up to 1300 MW on Monday 17th June 2024 from 1200 to 1800hrs.
This test includes a trip and reclose of a line in northern NSW.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade
Ben Blake
AEMO Operations