Filter by category
Filter by Date
NON-CONFORMANCE Region QLD1 Tuesday, 25 June 2024
NON-CONFORMANCE QLD1 Region Tuesday, 25 June 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 25/06/2024 09:35 to 25/06/2024 09:50
Amount: -40 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 24 June 2024
NON-CONFORMANCE QLD1 Region Monday, 24 June 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 24/06/2024 18:30 to 24/06/2024 20:20
Amount: 49 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 24 June 2024
NON-CONFORMANCE QLD1 Region Monday, 24 June 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 24/06/2024 19:30 to 24/06/2024 20:20
Amount: -42 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 24 June 2024
NON-CONFORMANCE QLD1 Region Monday, 24 June 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 24/06/2024 06:40 to 24/06/2024 07:00
Amount: 19 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Sunday, 23 June 2024
NON-CONFORMANCE QLD1 Region Sunday, 23 June 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 23/06/2024 19:05 to 23/06/2024 20:00
Amount: -35 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Sunday, 23 June 2024
NON-CONFORMANCE QLD1 Region Sunday, 23 June 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 23/06/2024 12:15 to 23/06/2024 12:55
Amount: -29 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Saturday, 22 June 2024
NON-CONFORMANCE QLD1 Region Saturday, 22 June 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: TARONG#2
Duration: 22/06/2024 20:10 to 22/06/2024 21:05
Amount: -18 MW
Constraint: NC-Q_TARONG#2
Auto-generated on behalf of Manager NEM Real Time Operations
Network Augmentation Commissioned - QLD Region - 21/06/2024
Network Augmentation Commissioned - QLD Region - 21/06/2024
Commissioned:
H90 Tully South - T48 Tully 7162 132kV line
H90 Tully South No.1 275kV /132 kV transformer
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Friday, 21 June 2024
NON-CONFORMANCE QLD1 Region Friday, 21 June 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 21/06/2024 11:25 to 21/06/2024 12:05
Amount: 39 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations