116902RECLASSIFY CONTINGENCY06/06/2024 12:31:05 PM

Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Duration: 06/06/2024 12:30 until further notice

Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Auto-generated on behalf of Manager NEM Real Time Operations
116890PRICES SUBJECT TO REVIEW04/06/2024 06:55:22 PM

[EventId:202406041900_review] Prices for interval 04-Jun-2024 19:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1855 hrs on 4 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Jun-2024 19:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
116889PRICES SUBJECT TO REVIEW04/06/2024 06:50:22 PM

[EventId:202406041855_review] Prices for interval 04-Jun-2024 18:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1850 hrs on 4 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Jun-2024 18:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
116888PRICES SUBJECT TO REVIEW04/06/2024 06:45:24 PM

[EventId:202406041850_review] Prices for interval 04-Jun-2024 18:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1845 hrs on 4 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Jun-2024 18:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
116887PRICES SUBJECT TO REVIEW04/06/2024 06:40:24 PM

[EventId:202406041845_review] Prices for interval 04-Jun-2024 18:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1840 hrs on 4 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Jun-2024 18:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
116886PRICES SUBJECT TO REVIEW04/06/2024 06:35:16 PM

[EventId:202406041840_review] Prices for interval 04-Jun-2024 18:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1835 hrs on 4 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Jun-2024 18:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
116885PRICES SUBJECT TO REVIEW04/06/2024 06:30:17 PM

[EventId:202406041835_review] Prices for interval 04-Jun-2024 18:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1830 hrs on 4 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Jun-2024 18:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
116883NON-CONFORMANCE04/06/2024 06:00:20 AM

NON-CONFORMANCE Region VIC1 Tuesday, 4 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Tuesday, 4 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MACARTH1
Duration: 04/06/2024 05:55 to 04/06/2024 06:00
Amount: 34 MW
Constraint: NC-V_MACARTH1

Auto-generated on behalf of Manager NEM Real Time Operations
116878RECLASSIFY CONTINGENCY02/06/2024 04:54:31 PM

Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Cancellation time: 02/06/2024 16:54

Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Refer AEMO Electricity Market Notice 116876