Update - Possible intervention to manage power system security in SA region
Update - Possible intervention to manage power system security in SA region
Refer AEMO Electricity Market Notice 111991
The synchronous generating units currently expected to be synchronised in SA from 0100 hrs 06/12/2023 will be inadequate to maintain a secure operating state in SA .
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 03/12/2023
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 03/12/2023
Refer Market Notice 111957
The AEMO Intervention Event and all associated directions are cancelled from 1530 hrs 04/12/2023
Manager NEM Real Time Operations
Possible intervention to manage power system security in SA Region
Possible intervention to manage power system security in SA Region
The synchronous generating units currently expected to be synchronised in SA from 0750 hrs 05/12/2023 will be inadequate to maintain a secure operating state in SA.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 03/12/2023
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 111973 is cancelled at 1820 hrs 03/12/2023.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 03/12/2023
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Periods:
[1.] From 1800 hrs 03/12/2023 to 1930 hrs 03/12/2023.
The forecast capacity reserve requirement is 1293 MW.
The minimum capacity reserve available is 1168 MW.
[2.] From 2130 hrs 03/12/2023 to 2200 hrs 03/12/2023.
The forecast capacity reserve requirement is 1308 MW.
The minimum capacity reserve available is 1298 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region [beginning] on 03/12/2023
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 111962 is cancelled at 1530 hrs 03/12/2023.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 02/12/2023
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 02/12/2023
Refer Market Notice 111935
The AEMO Intervention Event and all associated directions are cancelled from 1630 hrs 03/12/2023
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 08/12/2023
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1630 hrs 08/12/2023 to 1800 hrs 08/12/2023.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1303 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 03/12/2023
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Periods:
[1.] From 1830 hrs 03/12/2023 to 1900 hrs 03/12/2023.
The forecast capacity reserve requirement is 1290 MW.
The minimum capacity reserve available is 1287 MW.
[2.] From 2130 hrs 03/12/2023 to 2200 hrs 03/12/2023.
The forecast capacity reserve requirement is 1308 MW.
The minimum capacity reserve available is 1253 MW.
Manager NEM Real Time Operations