Filter by category
Filter by Date
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/12/2023
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 112160 has been updated at 1400 hrs 11/12/2023 to the following:
From 1530 hrs to 2000 hrs 14/12/2023.
The forecast capacity reserve requirement is 1385 MW.
The minimum capacity reserve available is 700 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 14/12/2023
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1700 hrs to 2030 hrs 14/12/2023.
The forecast capacity reserve requirement is 1287 MW.
The minimum capacity reserve available is 1019 MW.
AEMO Operations
Non-credible contingency event - SA region - 11/12/2023
Non-credible contingency event - SA region - 11/12/2023
At 0444 hrs the Mintaro - Waterloo 132 kV Line tripped and the Clare North - Mintaro 132 kV Line tripped at the Mintaro end only.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/12/2023.
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 112042 has been updated at 1530 hrs 10/12/2023 to the following:
From 1600 hrs 14/12/2023 to 1830 hrs 14/12/2023.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1076 MW.
Manager NEM Real Time Operations
[EventId:202312091805_confirmed] Prices for interval 09-Dec-2023 18:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1825 hrs on 9 December 2023
PRICES ARE NOW CONFIRMED for trading interval 09-Dec-2023 18:05.
In accordance with Market Notice 112141 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202312091825_confirmed] Prices for interval 09-Dec-2023 18:25 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1825 hrs on 9 December 2023
PRICES ARE NOW CONFIRMED for trading interval 09-Dec-2023 18:25.
In accordance with Market Notice 112145 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202312091820_confirmed] Prices for interval 09-Dec-2023 18:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1825 hrs on 9 December 2023
PRICES ARE NOW CONFIRMED for trading interval 09-Dec-2023 18:20.
In accordance with Market Notice 112144 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202312091815_confirmed] Prices for interval 09-Dec-2023 18:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1825 hrs on 9 December 2023
PRICES ARE NOW CONFIRMED for trading interval 09-Dec-2023 18:15.
In accordance with Market Notice 112143 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202312091810_confirmed] Prices for interval 09-Dec-2023 18:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1825 hrs on 9 December 2023
PRICES ARE NOW CONFIRMED for trading interval 09-Dec-2023 18:10.
In accordance with Market Notice 112142 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.