Update - Non-credible contingency event - SA region - 11/12/2023
Update - Non-credible contingency event - SA region - 11/12/2023
Refer AEMO Electricity Market Notice 112181
At 1554 hrs the remaining Mintaro - Waterloo 132 kV Line was returned to service.
The following constraint set(s) revoked:
S-X-MNWT+CB
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Update - Possible intervention to manage power system security in SA region
Update - Possible intervention to manage power system security in SA region
Refer AEMO Electricity Market Notice 112176
The synchronous generating units currently expected to be synchronised in SA from 0900 hrs 12/12/2023 will be inadequate to maintain a secure operating state in SA .
AEMO estimates that, in the absence of sufficient market response by 0800 hrs 12/12/2023, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 14/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112179 is cancelled at 1400 hrs 11/12/2023.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 14/12/2023
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1630 hrs 14/12/2023 to 1800 hrs 14/12/2023.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 655 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 08/12/2023
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 08/12/2023
Refer Market Notice 112159
The AEMO Intervention Event and all associated directions are cancelled from 1400 hrs 11/12/2023
Manager NEM Real Time Operations
Possible intervention to manage power system security in SA Region
Possible intervention to manage power system security in SA Region
The synchronous generating units currently expected to be synchronised in SA from 0700 hrs 12/12/2023 will be inadequate to maintain a secure operating state in SA.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
NEM Local Temperature Alerts for VIC from 11 Dec 2023 to 15 Dec 2023
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
VIC
Mildura Ap (39+ Deg C): 12th Dec
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Non-credible contingency event - SA region - 11/12/2023
Non-credible contingency event - SA region - 11/12/2023
At 0444 hrs the Mintaro - Waterloo 132 kV Line tripped and the Clare North - Mintaro 132 kV Line tripped at the Mintaro end only.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Network Augmentation Commissioned - SA Region - 10/12/2023
Network Augmentation Commissioned - SA Region - 10/12/2023
Commissioned: Robertstown - Bundey No. 1 275 kV Line
Bundey 275 kV Swtichyard
Manager NEM Real Time Operations