Market Notices

117027GENERAL NOTICE17/06/2024 10:59:14 AM

QNI Minor testing (Qld to NSW) 17th June 2024

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 114742

There is an opportunity for testing QNI Minor for flows from Qld to NSW up to 1300 MW on Monday 17th June 2024 from 1200 to 1800hrs.

This test includes a trip and reclose of a line in northern NSW.

Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade

Ben Blake
AEMO Operations
117021RESERVE NOTICE15/06/2024 08:03:58 PM

Cancellation of Actual (LOR1) condition in the NSW region - 15/06/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 15/06/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.117020 is cancelled at 1900 hrs 15/06/2024.

Manager NEM Real Time Operations
117020RESERVE NOTICE15/06/2024 05:14:10 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 15/06/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 15/06/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 1780 MW
The minimum capacity reserve available is 1446 MW

Manager NEM Real Time Operations
116907INTER-REGIONAL TRANSFER07/06/2024 07:56:38 AM

Inter-Regional Transfer limit variation - Outage Cancelled - Planned outage of Moorabool - Mortlake No.2 500 kV Line in Vic region on 7 June 2024.

AEMO ELECTRICITY MARKET NOTICE

The Moorabool - Mortlake No.2 500kV Line in Victoria (VIC) region was planned to be on an outage on 07/06/2024. This outage has been withdrawn by the TNSP.

Constraint sets associated with this outage have been revoked.
I-VS+LKB_050, I-VS_050, V-MLMO

These constraint sets contains equations with the following interconnectors on the LHS.
V-SA, VIC1-NSW1, T-V-MNSP1, V-S-MNSP1

Refer to the AEMO Network Outage Scheduler (NOS) for further information.

Manager NEM Real Time Operations
116906INTER-REGIONAL TRANSFER07/06/2024 04:39:57 AM

Inter-regional transfer limit variation - Heywood - Tarrone No.1 500kV line - VIC region - 07/06/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Heywood - Tarrone No.1 500kV line - VIC region - 07/06/2024

At 0406 hrs 07/06/2024 there was an unplanned outage of Heywood - Tarrone No.1 500kV line

The following constraint set(s) invoked at 0415 hrs 07/06/2024
V-HYTR

This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1, T-V-MNSP1, V-S-MNSP1, V-SA, VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
116904INTER-REGIONAL TRANSFER06/06/2024 02:29:13 PM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No 1 Leg of Directlink, with the No.2 Leg of Directlink previously out-of-service.

The following constraint set was invoked at 1425 hrs 06/06/2024

N-X_MBTE_2

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
116901INTER-REGIONAL TRANSFER06/06/2024 11:22:44 AM

Inter-regional transfer limit variation - Tarrone K1 500/132 kV Transformer - VIC region - 06/06/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Tarrone K1 500/132 kV Transformer - VIC region - 06/06/2024

At 1058 hrs 06/06/2024 there was an unplanned outage of Tarrone K1 500/132 kV Transformer.

The following constraint set(s) invoked at 1115 hrs 06/06/2024
V-TRTS_BUS_CB_500

This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1,V-S-MNSP1,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
116900INTER-REGIONAL TRANSFER06/06/2024 08:05:12 AM

Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)

AEMO has been notified that the controls to vary Directlink output are unavailable until further notice.

Constraint set I-CTRL_ISSUE_TE invoked from 0805 hrs.

The constraint set contains equations with the following interconnector on the LHS:

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details


Manager NEM Real Time Operations
116899GENERAL NOTICE05/06/2024 12:11:55 PM

Network Augmentation Commissioned - QLD Region - 05/06/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - QLD Region - 05/06/2024

H20 Broadsound 275 kV Bus Reactor 1 (150 MVAr) has been commissioned as at 1043 hrs.

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm