117300INTER-REGIONAL TRANSFER06/07/2024 10:34:25 AM

Inter-regional transfer limit variation -Murraylink - SA region - 06/07/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation -Murraylink - SA region - 06/07/2024

A planned outage of Murraylink in the SA region was scheduled from 0700 hrs 28/06/2024 to 1700 hrs 09/07/2024.

The outage has been completed and Murraylink returned to service at 1035 hrs 06/07/2024

Constraint set(s) revoked: I-MURRAYLINK

Manager NEM Real Time Operations
117296MARKET SYSTEMS05/07/2024 03:30:41 PM

CHG0090731 | Production | MSATS and eMDM July Maintenance Release

Change Number: CHG0090731

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)

Change Title: MSATS and eMDM July Maintenance Release
Change Start Date & Time: 14/07/2024 10:00:00 AEST
Change End Date & Time: 14/07/2024 18:00:00 AEST
Outage Start Date & Time: 14/07/2024 10:00:00 AEST
Outage End Date & Time: 14/07/2024 18:00:00 AEST

Environment: Production

Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

NOTE: The Outage is from 10:00 to 18:00 AEST which is 4 hours longer than the agreed maintenace window of 10:00 to 14:00 AEST.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

CDR and CDP will not be available during the outage period.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
117290INTER-REGIONAL TRANSFER04/07/2024 02:18:46 PM

Inter-regional transfer limit variation - Crookwell- Gullen Range 3H and Bannaby - Crookwell 61 330 kV lines - NSW region - 04/07/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Crookwell- Gullen Range 3H and Bannaby - Crookwell 61 330 kV lines - NSW region - 04/07/2024

A planned outage of Crookwell- Gullen Range 3H and Bannaby - Crookwell 61 330 kV lines in the NSW region was scheduled from 0800 hrs 03/07/2024 to 1700 hrs 04/07/2024.

The outage has been completed and Crookwell- Gullen Range 3H and Bannaby - Crookwell 61 330 kV lines returned to service at 1405 hrs 04/07/2024

Constraint set(s) revoked: N-BYCR_61_15M and N-CRGR_3H

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.


Manager NEM Real Time Operations
117289INTER-REGIONAL TRANSFER04/07/2024 11:04:20 AM

Inter-regional transfer limit variation - [outage element] - NSW region - 04/07/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Lismore - Dunoon 9U7 132 kV line - NSW region - 04/07/2024

A planned outage of Lismore - Dunoon 9U7 132 kV line in the NSW region was scheduled from 0732 hrs 02/07/2024 to 1700 hrs 19/07/2024.

The outage has been completed and Lismore - Dunoon 9U7 132 kV line returned to service at 1105 hrs 04/07/2024

Constraint set(s) revoked: N-LSDU_9U6

This constraint set contains equations with the following interconnectors on the LHS.
N-Q-MNSP1

Manager NEM Real Time Operations
117258MARKET SYSTEMS01/07/2024 10:32:38 AM

CHG0090790 | Completed | Production | Maintenance activities to be performed on the Gas Short Term Trading Market Systems Production.

Change Number: CHG0090790

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: Gas FRC - CATS

Change Title: Maintenance activities to be performed on the Gas Short Term Trading Market Systems Production.

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
117257MARKET SYSTEMS01/07/2024 10:27:56 AM

CHG0090718 | Production | QLD Marketnet Router Replacement

Change Number: CHG0090718

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Market Network

Change Title: QLD Marketnet Router Replacement

Change Start Date & Time: 10/08/2024 13:00:24 AEST

Change End Date & Time: 10/08/2024 17:00:24 AEST

Outage Start Date & Time:

Outage End Date & Time:

Environment: Production

Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage:

IPWAN Participants - A brief interuption of up to 60 seconds while services are failover from QLD to NSW Datacenter.

Lan-2-Lan VPN Participants (IPSEC) - Up to 2 hour outage for participants who have established their VPN connection/s via the AEMO QLD datacenter termination point (202.44.76.10) only - All L2L connections should be established to both QLD / NSW.

Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO NSW datacenter termination point (202.44.78.10) prior to this scheduled outage.

B2B VPN - No impact is expected.

SSL VPN Participants: None expected as SSL VPN's are hosted on a different device.

GASHUB: No impact is expected as GASHUB will be failed over to the NSW Datacenter.

Other Impacts will have been communicated in advance.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
117256MARKET SYSTEMS01/07/2024 10:24:08 AM

CHG0090717 | Production | NSW Marketnet Router Replacement

Change Number: CHG0090717

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Market Network

Change Title: NSW Marketnet Router Replacement

Change Start Date & Time: 27/07/2024 13:00:06 AEST

Change End Date & Time: 27/07/2024 17:00:06 AEST

Outage Start Date & Time:

Outage End Date & Time:

Environment: Production

Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage:

IPWAN Participants - A brief interuption of up to 60 seconds while services are failover from NSW to QLD Datacenter.

Lan-2-Lan VPN Participants (IPSEC) - Up to 2 hour outage for participants who have established their VPN connection/s via the AEMO NSW datacenter termination point (202.44.78.10) only - All L2L connections should be established to both QLD / NSW.

Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO QLD datacenter termination point (202.44.76.10) prior to this scheduled outage.

B2B VPN - No impact is expected.

SSL VPN Participants: None expected as SSL VPN's are hosted on a different device.

GASHUB: No impact is expected as GASHUB is currently operating out of BNE Datacenter.

Other Impacts will have been communicated in advance.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
117255MARKET SYSTEMS01/07/2024 10:19:12 AM

CHG0090719 | Production | Change to MarketNet SSL VPN


Change Number: CHG0090719
Notification issued to: Market Notice
Notification Type: Initial

Change Type: Normal

Service/ Component: Market Network

Change Title: Change to MarketNet SSL VPN

Change Start Date & Time: 10/07/2024 18:00:21 AEST

Change End Date & Time: 10/07/2024 22:00:21 AEST

Outage Start Date & Time:

Outage End Date & Time:

Environment: Production

Participant Impact and Requirements: A change to the MarketNet SSL VPN connection will take place on the 10th July 2024 between 6pm and 10PM AEST. There will be a 30 minute period during this change where no new VPN Connections will be able to be established.

Post the change window, participants running on an older version of the software may receive a message that the Anyconnect VPN client needs to be updated. This process should be automatic and once done VPN connectivity should be as normal.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.


117246MARKET SYSTEMS28/06/2024 05:56:36 PM

CHG0090718 | Production | QLD Marketnet Router Replacement

Change Number: CHG0090718

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Market Network

Change Title: QLD Marketnet Router Replacement

Change Start Date & Time: 10/08/2024 13:00:24 AEST

Change End Date & Time: 10/08/2024 17:00:24 AEST

Outage Start Date & Time:
Outage End Date & Time:

Environment: Production

Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage:

IPWAN Participants - A brief interuption of up to 60 seconds while services are failover from QLD to NSW Datacenter.

Lan-2-Lan VPN Participants (IPSEC) - Up to 2 hour outage for participants who have established their VPN connection/s via the AEMO QLD datacenter termination point (202.44.76.10) only - All L2L connections should be established to both QLD / NSW.

Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO NSW datacenter termination point (202.44.78.10) prior to this scheduled outage.

B2B VPN - No impact is expected.

SSL VPN Participants: None expected as SSL VPN's are hosted on a different device.

GASHUB: No impact is expected as GASHUB will be failed over to the NSW Datacenter.

Other Impacts will have been communicated in advance.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm