Filter by category
Filter by Date
NON-CONFORMANCE Region VIC1 Saturday, 1 June 2024
NON-CONFORMANCE VIC1 Region Saturday, 1 June 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: YWPS2
Duration: 01/06/2024 07:25 to 01/06/2024 07:40
Amount: -8 MW
Constraint: NC-V_YWPS2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Tuesday, 21 May 2024
NON-CONFORMANCE NSW1 Region Tuesday, 21 May 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BW04
Duration: 21/05/2024 16:30 to 21/05/2024 16:35
Amount: -19 MW
Constraint: NC-N_BW04
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Tuesday, 21 May 2024
NON-CONFORMANCE NSW1 Region Tuesday, 21 May 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BW04
Duration: 21/05/2024 10:45 to 21/05/2024 10:50
Amount: -22 MW
Constraint: NC-N_BW04
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 20/05/2024
Cancellation of Actual (LOR1) condition in the NSW region - 20/05/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.116730 is cancelled at 1910 hrs 20/05/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 20/05/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 20/05/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 1630 MW
The minimum capacity reserve available is 1028 MW
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Sunday, 19 May 2024
NON-CONFORMANCE QLD1 Region Sunday, 19 May 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: PUMP2
Duration: 19/05/2024 07:35 to 19/05/2024 07:40
Amount: 240 MW
Constraint: NC-Q_PUMP2
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 18/05/2024
Cancellation of Actual (LOR1) condition in the NSW region - 18/05/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No. 116688 is cancelled at 1840 hrs 18/05/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 18/05/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 18/05/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs
The capacity reserve requirement is 1430 MW
The minimum capacity reserve available is 1314 MW
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Saturday, 18 May 2024
NON-CONFORMANCE QLD1 Region Saturday, 18 May 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 18/05/2024 02:40 to 18/05/2024 02:45
Amount: -14 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations