Inter-regional transfer limit variation - Dapto - Marulan 8 Line - NSW region - 08/02/2024
Inter-regional transfer limit variation - Dapto - Marulan 8 Line - NSW region - 08/02/2024
At 1015 hrs 08/02/2024 there was a short notice outage of Dapto - Marulan 8 Line
The following constraint set(s) invoked at 1015 hrs 08/02/2024
N-DTMN_8_15M
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - South Pine SVC - QLD region - 07/02/2024
Inter-regional transfer limit variation - South Pine SVC - QLD region - 07/02/2024
At 1850 hrs 07/02/2024 there was an unplanned outage of the South Pine SVC.
The following constraint set(s) invoked at 1855 hrs 07/02/2024
Q-SP_VC
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Greenbank 275kV SVC - QLD region - 06/02/2024
Inter-regional transfer limit variation - Greenbank 275kV SVC - QLD region - 06/02/2024
At 2102 hrs 06/02/2024 there was an unplanned outage of the Greenbank 275kV SVC
The following constraint set(s) invoked at 2110 hrs 06/02/2024
Q-GB_VC
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Cancellation - Non-credible contingency event - QLD region - 27/01/2024
Cancellation - Non-credible contingency event - QLD region - 27/01/2024
Refer AEMO Electricity Market Notice 113825
At 0138 hrs the Gin Gin (H6) No.2 275 kV Busbar tripped.
AEMO has received further information and now determines this was not a non-credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - QLD region - 27/01/2024
Non-credible contingency event - QLD region - 27/01/2024
At 0138 hrs the Gin Gin (H6) No.2 275 kV Busbar tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Update - Non-credible contingency event - QLD region - 23/01/2024
Update - Non-credible contingency event - QLD region - 23/01/2024
Refer AEMO Electricity Market Notice 113659
At 1122 hrs the H35 Strathmore No2 275 kV bus was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
Nebo - Strathmore 878 275 kV line to remain out of service.
See Network Outage Scheduler (NOS) for further details.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - QLD region - 23/01/2024
Non-credible contingency event - QLD region - 23/01/2024
At 0957 hrs the Strathmore No 2 275 kV bus tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
The following constraint set(s) invoked
Q-NESTM
Q-X_NQ_275_FDR+BUS
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Hazelwood - South Morang No2 500 kV Line - VIC region - 23/01/2024
Inter-regional transfer limit variation - Hazelwood - South Morang No2 500 kV Line - VIC region - 23/01/2024
At 0318 hrs 23/01/2024 there was an unplanned outage of Hazelwood - South Morang No2 500 kV Line.
The following constraint set(s) invoked at 0325 hrs 23/01/2024
V-HWSM
This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1,V-S-MNSP1,V-SA,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of the No 3 Leg of Directlink .
The following constraint set was invoked at 1510 hrs 18/01/2024
N-MBTE_1
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations