Inter-regional transfer limit variation - Collector WF - Yass 3L 330KV Line - NSW region - 27/05/2024
Inter-regional transfer limit variation - Collector WF - Yass 3L 330KV Line - NSW region - 27/05/2024
A planned outage of Collector WF - Yass 3L 330KV Line in the NSW region was scheduled from 0600 hrs 03/04/2024 to 1500 hrs 27/05/2024.
The outage has been rescheduled to be completed by 1500 hrs 07/06/2024.
Constraint set(s) invoked: N-CTYS_3L_WG_CLOSE
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1-QLD1
V-S-MNSP1
VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of the No 2 Leg of Directlink .
The following constraint set was invoked at 2340 hrs 23/05/2024
N-MBTE_1
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Para 275kV 1 and 2 275kV SVCs - SA region - 22/05/2024
Inter-regional transfer limit variation - Para 275kV 1 and 2 275kV SVCs - SA region - 22/05/2024
At 1300 hrs 22/05/2024 there was a short notice outage of Para 275kV 1 and 2 275kV SVCs.
The following constraint set(s) invoked at 1300 hrs 22/05/2024
S-X_PA_VC_2
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Tuesday, 21 May 2024
NON-CONFORMANCE NSW1 Region Tuesday, 21 May 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BW04
Duration: 21/05/2024 16:30 to 21/05/2024 16:35
Amount: -19 MW
Constraint: NC-N_BW04
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Tuesday, 21 May 2024
NON-CONFORMANCE NSW1 Region Tuesday, 21 May 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BW04
Duration: 21/05/2024 10:45 to 21/05/2024 10:50
Amount: -22 MW
Constraint: NC-N_BW04
Auto-generated on behalf of Manager NEM Real Time Operations
Update Inter-Regional Transfer limit variation - Basslink 21/05/2024
Update Inter-Regional Transfer limit variation - Basslink
Refer AEMO Electricity Market Notice 116734
There was an unplanned outage of the Basslink interconnector at 0235 hrs. The Basslink interconnector has been returned to service.
The following constraint set was revoked at 0810 hrs 21/05/2024
I-BL_ZERO
The constraint set contains the following interconnector on the left hand side.
T-V-MNSP1
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Basslink 21/05/2024
Inter-Regional Transfer limit variation - Basslink
There has been an unplanned outage of the Basslink interconnector at 0235 hrs
The following constraint set was invoked at 0240 hrs 21/05/2024
I-BL_ZERO
The constraint set contains the following interconnector on the left hand side.
T-V-MNSP1
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Sunday, 19 May 2024
NON-CONFORMANCE QLD1 Region Sunday, 19 May 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: PUMP2
Duration: 19/05/2024 07:35 to 19/05/2024 07:40
Amount: 240 MW
Constraint: NC-Q_PUMP2
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-regional transfer limit variation - Tamworth - Armidale No. 86 330 kV Line - NSW region - 19/05/2024
Inter-regional transfer limit variation - Tamworth - Armidale No. 86 330 kV Line - NSW region - 19/05/2024
A planned outage of Tamworth - Armidale No. 86 330 kV Line in the NSW region was scheduled from 0800 hrs 07/05/2024 to 1800 hrs 20/05/2024.
The outage has been rescheduled to be completed by 1200 hrs 19/05/2024.
Constraint set(s) invoked:
N-ARTW_86
N-DM_SVC
N-TW_SVC
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1-QLD1
T-V-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations