Filter by category
Filter by Date
CHG0089027 | Cancelled | Pre-Production | Pre-Prod eMDM May Maintenance Release
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: MDM - Meter Data Management
Change Title: Pre-Prod eMDM May Maintenance Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
Planned outage of Gordon - Chapel St No. 1 220 kV line in the TAS region on 26/04/2024
The Gordon - Chapel St No. 1 220 kV line in the Tasmania (TAS) region is planned to be out of service from 1030 hrs on 26/04/2024 to 1500 hrs on 26/04/2024
A credible contingency event during this planned outage could cause a large reduction in generation in TAS.
Refer AEMO Network Outage Schedule (NOS) for further details.
Manager NEM Real Time Operations
CHG0089027 | Pre-Production | Pre-Prod eMDM May Maintenance Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MDM - Meter Data Management
Change Title: Pre-Prod eMDM May Maintenance Release
Change Start Date & Time: 29/04/2024 13:00:00 AEST
Change End Date & Time: 29/04/2024 17:00:00 AEST
Outage Start Date & Time: 29/02/2024 13:00:00 AEST
Outage End Date & Time: 29/02/2024 15:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0087670 | Production | MSATS-CATS Production Maintenance
A URM outage will occur between 11:15:00 - 11:45:00 AEST and have an expected outage duration of upto 20 minutes. During this time users will not be able to have new login sessions into TMM, OPDMS, NOS or EMMS WebPortal. Users who are already logged in will not be impacted.
An MSATS outage will occur from 10:00:00 - 16:00:00 AEST.
Participants should be aware that:
o MSATS, Meter data processing, RM reports, B2B, B2M screen, NMI Discovery, CDR, CDP will not be available
o Production participant passwords will be retained
o Users that log out and users that try to log in once the URM outage has commenced will only be able to log in after URM outage is complete. Users that are already logged in before the outage will not be impacted
o MSATS and NOS Server FTP sessions will be disabled during the outage - Wholesale MMS FTP will still be available
o Plain English constraints will not be available during the URM outage timeframe via the EMMS web portal
o The redirection menu will be unavailable - https://menu.prod.nemnet.net.au
Report any impacts to the Support Hub -1300 236 600
CHG0088931 | Production | Planned System Maintenance activity.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMS NEM - Network Outage Scheduler (NOS)
Change Title: Planned System Maintenance activity.
Change Start Date & Time: 29/04/2024 11:00:00 AEST
Change End Date & Time: 29/04/2024 12:00:00 AEST
Outage Start Date & Time: 29/04/2024 11:00:00 AEST
Outage End Date & Time: 29/04/2024 12:00:00 AEST
Environment: Production
Participant Impact and Requirements: Network Outage Schedular (NOS) will be out of service during the maintenance activity. Please log off from NOS website during the outage. Users will have to log back in once the outage is completed. Please contact your NOS admin or AEMO support hub if your NOS account has been locked out after this change.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities.
CHG0088831 | Completed | Production | Identity Service Config Update in Production.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Identity Service (IDS)
Change Title: Identity Service Config Update in Production.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0088138 | Completed | Production | Brisbane MarketNet Firewall Refresh
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Firewall
Change Title: Brisbane MarketNet Firewall Refresh
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0088121 | Completed | Production | Production MSATS Lifecycle Maintenance
Change Number: CHG0088121
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Production MSATS Lifecycle Maintenance
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0088386 | Production | QLD Internet Router Refresh
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Internet Access
Change Title: QLD Internet Router Refresh
Change Start Date & Time: 04/05/2024 09:00:01 AEST
Change End Date & Time: 04/05/2024 14:00:01 AEST
Outage Start Date & Time: 04/05/2024 09:30:32 AEST
Outage End Date & Time: 04/05/2024 12:30:32 AEST
Environment: Production
Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage:
IPWAN Participants - Nil
Lan-2-Lan VPN Participants (IPSEC) - Up to 2 hour outage for participants who have established their VPN connection/s via the AEMO QLD datacenter termination point (202.44.76.10) only - All L2L connections should be established to both QLD / NSW.
Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO NSW datacenter termination point (202.44.78.10) prior to this scheduled outage.
B2B VPN - Up to 2 hour outage to TNSPs with B2B VPN to AEMO QLD Datacentre if VPN connection is only terminating in QLD only
SSL VPN Participants: None expected as DNS entry will be updated to remove QLD IP.
GASHUB: No impact is expected as GASHUB is currently operating out of NOR Datacenter.
Other Impacts will have been communicated in advance.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any