Filter by category
Filter by Date
NON-CONFORMANCE Region VIC1 Saturday, 2 March 2024
NON-CONFORMANCE VIC1 Region Saturday, 2 March 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GLRWNSF1
Duration: 02/03/2024 13:45 to 02/03/2024 13:55
Amount: 110 MW
Constraint: NC-V_GLRWNSF1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Saturday, 2 March 2024
NON-CONFORMANCE QLD1 Region Saturday, 2 March 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: STAN-2
Duration: 02/03/2024 07:55 to 02/03/2024 08:05
Amount: 21 MW
Constraint: NC-Q_STAN-2
Auto-generated on behalf of Manager NEM Real Time Operations
Non-credible contingency event - QLD region - 28/02/2024
Non-credible contingency event - QLD region - 28/02/2024
At 1029 hrs the Tully - Cardwell No.7389 132 kV Line tripped and auto reclosed and Ross - Woree No. 8905 275 kV Line tripped and auto reclosed.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 26 February 2024
NON-CONFORMANCE QLD1 Region Monday, 26 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 26/02/2024 23:10 to 26/02/2024 23:15
Amount: -32 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Friday, 23 February 2024
NON-CONFORMANCE NSW1 Region Friday, 23 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BW01
Duration: 23/02/2024 16:35 to 23/02/2024 17:35
Amount: 43 MW
Constraint: NC-N_BW01
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Friday, 23 February 2024
NON-CONFORMANCE QLD1 Region Friday, 23 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: PUMP1
Duration: 23/02/2024 09:05 to 23/02/2024 09:10
Amount: 243 MW
Constraint: NC-Q_PUMP1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Thursday, 22 February 2024
NON-CONFORMANCE SA1 Region Thursday, 22 February 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: HPRG1, HPRL1
Aggregate Dispatch Group: HORNSDPR_ADG1
Duration: 22/02/2024 14:55 to 22/02/2024 15:00
Amount: 12 MW
Constraint: NC-S_HORNSDPR_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Thursday, 22 February 2024
NON-CONFORMANCE VIC1 Region Thursday, 22 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MERCER01
Duration: 22/02/2024 05:40 to 22/02/2024 05:55
Amount: 127 MW
Constraint: NC-V_MERCER01
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 22 February 2024
NON-CONFORMANCE NSW1 Region Thursday, 22 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP6
Duration: 22/02/2024 04:20 to 22/02/2024 04:30
Amount: -29 MW
Constraint: NC-N_VP6
Auto-generated on behalf of Manager NEM Real Time Operations