Market Notices

112223GENERAL NOTICE13/12/2023 10:49:32 AM

NEM Local Temperature Alerts for QLD from 13 Dec 2023 to 17 Dec 2023

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

QLD
Dalby Ap (37+ Deg C): 17th Dec

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
112215GENERAL NOTICE12/12/2023 11:11:25 PM

Network Augmentation Commissioned - SA Region - 12/12/2023

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - SA Region - 12/12/2023

Commissioned: Robertstown - Bundey No. 2 275 kV Line

Manager NEM Real Time Operations
112201RECALL GEN CAPACITY12/12/2023 10:59:40 AM

Request for Generator Recall Information for 14/12/2023 for QLD Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 112198. Additional generation in QLD could assist in alleviating the forecast LOR condition in NSW.

Please provide Generator Recall Information for the period 14/12/2023, by 1200 hrs on 13/12/2023 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

AEMO Operations
112200RECALL GEN CAPACITY12/12/2023 11:01:01 AM

Request for Generator Recall Information for 14/12/2023 for NSW Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 112198.

Please provide Generator Recall Information for the period 14/12/2023, by 1200 hrs on 13/12/2023 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

AEMO Operations
112172GENERAL NOTICE11/12/2023 11:08:03 AM

NEM Local Temperature Alerts for VIC from 11 Dec 2023 to 15 Dec 2023

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

VIC
Mildura Ap (39+ Deg C): 12th Dec

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
112162GENERAL NOTICE10/12/2023 09:05:21 PM

Network Augmentation Commissioned - SA Region - 10/12/2023

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - SA Region - 10/12/2023

Commissioned: Robertstown - Bundey No. 1 275 kV Line
Bundey 275 kV Swtichyard

Manager NEM Real Time Operations
112154RESERVE NOTICE09/12/2023 06:50:27 PM

Cancellation of Actual (LOR1) condition in the NSW region - 09/12/2023

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 09/12/2023

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.112137 is cancelled at 1850 hrs 09/12/2023.

Manager NEM Real Time Operations
112137RESERVE NOTICE09/12/2023 05:16:02 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/12/2023

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/12/2023

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.

The Actual LOR1 condition is forecast to exist until 1830 hrs.

The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1344 MW.

Manager NEM Real Time Operations
112120GENERAL NOTICE08/12/2023 05:35:38 PM

Network Augmentation Commissioned - NSW Region - 08/12/2023

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - NSW Region - 08/12/2023

Commissioned: Wellington - Wellington North Solar Farm 7H 330 kV Line

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm