Market Notices

113572RESERVE NOTICE21/01/2024 06:13:53 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 21/01/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 21/01/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is not forecast in Pre Dispatch

The capacity reserve requirement is 1360 MW
The minimum capacity reserve available is 1354 MW

Manager NEM Real Time Operations
113570RESERVE NOTICE21/01/2024 06:12:48 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 21/01/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 21/01/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs

The capacity reserve requirement is 1238 MW
The minimum capacity reserve available is 988 MW

Manager NEM Real Time Operations
113522RESERVE NOTICE19/01/2024 08:27:14 PM

Cancellation of Actual (LOR1) condition in the QLD region - 19/01/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 19/01/2024

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.113498 is cancelled at 2000 hrs 19/01/2024.

Manager NEM Real Time Operations
113498RESERVE NOTICE19/01/2024 05:44:26 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 19/01/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 19/01/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.
The Actual LOR1 condition is not forecast in Pre Dispatch

The capacity reserve requirement is 982 MW
The minimum capacity reserve available is 938 MW

Manager NEM Real Time Operations
113439RESERVE NOTICE18/01/2024 06:17:12 PM

Cancellation of Actual (LOR1) condition in the QLD region - 18/01/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 18/01/2024

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.113424 is cancelled at 1815 hrs 18/01/2024.

Manager NEM Real Time Operations
113424RESERVE NOTICE18/01/2024 03:46:27 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 18/01/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 18/01/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1530 hrs.
The Actual LOR1 condition is forecast to exist until 2000 hrs

The capacity reserve requirement is 952 MW
The minimum capacity reserve available is 857 MW

Manager NEM Real Time Operations
113416INTER-REGIONAL TRANSFER18/01/2024 03:14:09 PM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No 3 Leg of Directlink .

The following constraint set was invoked at 1510 hrs 18/01/2024

N-MBTE_1

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
113395INTER-REGIONAL TRANSFER17/01/2024 09:40:50 PM

Inter-regional transfer limit variation - Bulli Creek - Dumaresq 8M 330 kV line - QLD region - 17/01/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Bulli Creek - Dumaresq 8M 330 kV line - QLD region - 17/01/2024

At 2115 hrs 17/01/2024 there was an unplanned outage of Bulli Creek - Dumaresq 8M 330 kV line.

The following constraint set(s) invoked at 2130 hrs 17/01/2024
I-BCDM_ONE, N-DM_SVC, N-TW_SVC, N-X_8L+DM+TW_SVC, N-X_DM+LS+TW_SVC

This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,T-V-MNSP1,N-Q-MNSP1,V-S-MNSP1,V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
113201INTER-REGIONAL TRANSFER11/01/2024 10:08:48 AM

Inter-regional transfer limit variation - South East CB6611 - SA region - 11/01/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - South East CB6611 - SA region - 11/01/2024

At 0955 hrs 11/01/2024 there was an short notice outage of South East CB6611.

The following constraint set(s) invoked at 0955 hrs 11/01/2024
S-SECB6611_10

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations