STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/02/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 114070 has been updated at 1400 hrs 01/02/2024 to the following:
From 1300 hrs to 2000 hrs 06/02/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/02/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 114075 has been updated at 1400 hrs 01/02/2024 to the following:
From 1230 hrs to 2130 hrs 05/02/2024.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 685 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 06/02/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 114068 has been updated at 1400 hrs 01/02/2024 to the following:
From 1800 hrs to 1930 hrs 06/02/2024.
The forecast capacity reserve requirement is 1264 MW.
The minimum capacity reserve available is 944 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 05/02/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1830 hrs to 1900 hrs 05/02/2024.
The forecast capacity reserve requirement is 1267 MW.
The minimum capacity reserve available is 1151 MW.
AEMO Operations
Cancellation of a Non-Credible Contingency Event: Strathmore ? Clare South No.7208 132 kV line and Strathmore ? Clare South tee King Creek No.7128/2 132 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Strathmore ? Clare South No.7208 132 kV and Strathmore ? Clare South tee King Creek No.7128/2 132 kV
Cancellation time: 01/02/2024 13:34
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 114105
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Strathmore ? Clare South No.7208 132 kV line and Strathmore ? Clare South tee King Creek No.7128/1 132 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Strathmore ? Clare South No.7208 132 kV and Strathmore ? Clare South tee King Creek No.7128/1 132 kV
Cancellation time: 01/02/2024 13:34
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 114104
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Collinsville - Stoney Creek 7306 132KV LINE line and Collinsville - Newlands 7121 132KV LINE line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Collinsville - Stoney Creek 7306 132KV LINE and Collinsville - Newlands 7121 132KV LINE
Cancellation time: 01/02/2024 13:34
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 114103
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Collinsville North - Proserpine No.7125 132 kV line and Collinsville North - Proserpine No.7126 132 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Collinsville North - Proserpine No.7125 132 kV and Collinsville North - Proserpine No.7126 132 kV
Cancellation time: 01/02/2024 13:34
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 114102
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Ross - Chalumbin No.857 275 kV line and Ross - Chalumbin No.858 275 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Ross - Chalumbin No.857 275 kV and Ross - Chalumbin No.858 275 kV
Duration: 01/02/2024 13:17 until further notice
Constraint set(s) invoked:
Q-RSCH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations