Filter by category
Filter by Date
CHG0085737 | Pre-Production | Pre-production EMMS database refresh
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System
Change Title: Pre-production EMMS database refresh
Change Start Date & Time: 26/02/2024 08:00:00 AEST
Change End Date & Time: 17/03/2024 17:30:00 AEST
Outage Start Date & Time: 04/03/2024 08:00:00 AEST
Outage End Date & Time: 08/03/2024 19:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: The pre-production EMMS environment will be refreshed with production data (NEM, WARE, SETTLEMENTS & GSH databases).
The Electricity Market Management System (EMMS) and Gas Supply Hub (GSH) Pre-Production environment will be unavailable during the outage window.
Upon completion of the outage users will be required to log in to the GSH Trayport application using their Production credentials.Trayport passwords in Pre-Production environment will be replaced with their Production passwords
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0083624 | Completed | Production | A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Gas Hub
Change Title: A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0082609 | Completed | Production | MSATS-CATS Production Maintenance
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: MSATS-CATS Production Maintenance
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
[EventId:202402131320_confirmed] Prices for interval 13-Feb-2024 13:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1452 hrs on 14 February 2024
PRICES ARE NOW CONFIRMED for trading interval 13-Feb-2024 13:20.
In accordance with Market Notice 114583 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
- Over-Constrained Dispatch has been resolved for dispatch interval
Changed Prices ($/MWh)
TYPE
Region Original Adjusted
Price Price
ENERGY
NSW1 -$38.41 -$35.04
QLD1 -$40.60 -$36.57
LOWERREG
TAS1 $16,600.00 $9.88
RAISEREG
TAS1 $16,600.00 $150.68
This is an AEMO autogenerated Market Notice.
INC0126874 | RESOLVED | Overnight standing data updates not reflecting in MSATS Enterprise MDM
SERVICE INTERRUPTION - RESOLVED
The issue with the standing data updates not reflecting in MSATS Enterprise MDM has been resolved.
There are no further steps to be completed. The service is now fully restored, and no further communication will be released unless there is a change of status.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
CHG0082504 | Completed | Pre-Production | Removal of support of TLS Version 1.1 and lower
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Business to Business data exchange
Change Title: Removal of support of TLS Version 1.1 and lower
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
INC0126874 | Overnight standing data updates not reflecting in MSATS Enterprise MDM
SERVICE INTERRUPTION - ALERT
AEMO is experiencing a service interruption relating to the Market Settlement & Transfer Solution Enterprise MDM service.
The overnight MSATS CATS change requests are not reflected in the MSATS Enterprise MDM. This has also impacted the Meter Data ingestion.
MDPs are advised to not resend meter data files until advised or resolved notification for this incident has been received.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
Cancellation of Actual (LOR3) condition in the VIC region - 13/02/2024
Cancellation of Actual (LOR3) condition in the VIC region - 13/02/2024
The Actual LOR3 Condition in the VIC region advised in AEMO Electricity Market Notice No.114604 is cancelled at 1515 hrs 13/02/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 3 (LOR3) in the VIC region - 13/02/2024
Actual Lack Of Reserve Level 3 (LOR3) in the VIC region - 13/02/2024
Customer load shedding of non-interruptible load is occurring in the VIC region as a result of a shortfall of available capacity reserves.
An Actual LOR3 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the VIC region from 1420 hrs.
The Actual LOR3 condition is not forecast in Pre Dispatch.
The maximum load to be interrupted is up to 450 MW from 1420 hrs 13/02/2024
Manager NEM Real Time Operations