Market Notices

114714NON-CONFORMANCE14/02/2024 02:10:25 PM

NON-CONFORMANCE Region NSW1 Wednesday, 14 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Wednesday, 14 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: SUNRSF1
Duration: 14/02/2024 08:55 to 14/02/2024 14:10
Amount: 91 MW
Constraint: NC-N_SUNRSF1

Auto-generated on behalf of Manager NEM Real Time Operations
114669NON-CONFORMANCE13/02/2024 05:52:22 PM

NON-CONFORMANCE Region SA1 Tuesday, 13 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Tuesday, 13 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: TORRB4
Duration: 13/02/2024 17:45 to 13/02/2024 17:50
Amount: 14 MW
Constraint: NC-S_TORRB4

Auto-generated on behalf of Manager NEM Real Time Operations
114668NON-CONFORMANCE13/02/2024 05:51:32 PM

NON-CONFORMANCE Region SA1 Tuesday, 13 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Tuesday, 13 February 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: HPRG1, HPRL1
Aggregate Dispatch Group: HORNSDPR_ADG1
Duration: 13/02/2024 17:45 to 13/02/2024 17:50
Amount: 20 MW
Constraint: NC-S_HORNSDPR_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
114617NON-CONFORMANCE13/02/2024 02:55:18 PM

NON-CONFORMANCE Region VIC1 Tuesday, 13 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Tuesday, 13 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: YWPS4
Duration: 13/02/2024 14:50 to 13/02/2024 14:55
Amount: -25 MW
Constraint: NC-V_YWPS4

Auto-generated on behalf of Manager NEM Real Time Operations
114607LOAD SHED13/02/2024 02:35:06 PM

Load Shedding Direction in the Vic Region

AEMO ELECTRICITY MARKET NOTICE

Load Shedding Direction in the Vic Region

AEMO has directed load shedding commencing at 1420 hrs 13/02/2024
in the Victoria region to restore power system security.

The direction was issued under section 116 of the NEL, and was a clause 4.8.9 instruction under the NER.

Manager NEM Real Time Operations
114563NON-CONFORMANCE13/02/2024 12:10:15 PM

NON-CONFORMANCE Region QLD1 Tuesday, 13 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 13 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 13/02/2024 12:05 to 13/02/2024 12:10
Amount: 15 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
114556NON-CONFORMANCE13/02/2024 11:25:22 AM

NON-CONFORMANCE Region QLD1 Tuesday, 13 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 13 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 13/02/2024 11:10 to 13/02/2024 11:25
Amount: 10 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
114543NON-CONFORMANCE13/02/2024 08:50:21 AM

NON-CONFORMANCE Region SA1 Tuesday, 13 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Tuesday, 13 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WATERLWF
Duration: 13/02/2024 08:15 to 13/02/2024 08:50
Amount: 43 MW
Constraint: NC-S_WATERLWF

Auto-generated on behalf of Manager NEM Real Time Operations
114542NON-CONFORMANCE13/02/2024 05:00:12 AM

NON-CONFORMANCE Region NSW1 Tuesday, 13 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 13 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MP1
Duration: 13/02/2024 04:55 to 13/02/2024 05:00
Amount: 21 MW
Constraint: NC-N_MP1

Auto-generated on behalf of Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm