Inter-regional transfer limit variation - [outage element] - NSW region - 23/12/2023
Inter-regional transfer limit variation - [outage element] - NSW region - 23/12/2023
A planned outage of KEMPS CREEK No 2 525/345/34 kV Transformer in the NSW region was scheduled from 0600 hrs 23/12/2023 to 1200 hrs 23/12/2023.
The outage has been cancelled.
The following constraint set(s) invoked at 0600 hrs 23/12/2023
N-KC_TX
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q_MNSP1
NSW1-QLD1
VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Palmerston - Hadspen 2 220kV line - TAS region - 22/12/2023
Inter-regional transfer limit variation - Palmerston - Hadspen 2 220kV line - TAS region - 22/12/2023
At 1300 hrs 22/12/2023 there was a short notice outage of Palmerston - Hadspen 2 220kV line.
Constraint set(s) invoked: T-HAPM_220
This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V - MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation: Hazelwood - South Morang No 1 500 kV Line (VIC) - Voltage Control
The Hazelwood - South Morang No 1 500 kV Line has been de-energised to manage voltages in the Victoria region.
The following constraint set was invoked at 0600 hrs 17/12/2023
V-HWSM
The constraint set contains equations with the following interconnectors on the LHS.
T-V-MNSP
V-S-MNSP1
V-SA
VIC1-NSW1
Refer to AEMO Network Outage Scheduler (NOS) for return to service details
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Sydney West - Vineyard No 29 330kV line - NSW region - 17/12/2023
Inter-regional transfer limit variation - Sydney West - Vineyard No 29 330kV line - NSW region - 17/12/2023
At 0545 hrs 17/12/2023 there was a short notice outage of Sydney West - Vineyard No 29 330kV line.
Constraint set(s) invoked: N-SWVY_29
The following constraint set(s) invoked at 0545 hrs 17/12/2023
N-SWVY_29
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 14/12/2023
Cancellation of Actual (LOR1) condition in the NSW region - 14/12/2023
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.112357 is cancelled at 1940 hrs 14/12/2023.
Manager NEM Real Time Operations
Cancellation of Actual (LOR2) condition in the NSW region - 14/12/2023
Cancellation of Actual (LOR2) condition in the NSW region - 14/12/2023
The Actual LOR2 Condition in the NSW Region advised in AEMO Electricity Market Notice No.112362 is cancelled at 1810 hrs 14/12/2023.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 14/12/2023
Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 14/12/2023
An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR2 condition is not forecast in Pre Dispatch
The capacity reserve required is 690 MW
The minimum reserve available is 678 MW
AEMO is seeking an immediate market response.
An insufficient market response may require AEMO to implement a AEMO intervention event.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 14/12/2023
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 14/12/2023
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 1377 MW
The minimum capacity reserve available is 874 MW
Manager NEM Real Time Operations
Request for Generator Recall Information for 14/12/2023 for QLD Region
Refer to AEMO Electricity Market Notice no. 112198. Additional generation in QLD could assist in alleviating the forecast LOR condition in NSW.
Please provide Generator Recall Information for the period 14/12/2023, by 1200 hrs on 13/12/2023 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations