Direction - NSW region 05/09/2024
Direction - NSW region 05/09/2024
In accordance with clause 4.8.9(a)(1) of the National Electricity Rules, AEMO is issuing a direction to Snowy Hydro Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Snowy Hydro Limited - TUMUT3 TUMUT3 at 1405 hrs 05/09/2024
Type of resource: load
Required actions: maintain 0 MW output at 1405 hrs 05/09/2024 TUMUT3 Pump 4 and Pump 5
Services provided: Energy
Circumstances necessitating the Overload
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1440 hrs 05/09/2024
Snowy Hydro Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Declaration of electricity market resumption
Declaration of electricity market resumption
Refer initial AEMO Electricity Market Notice 118149
AEMO declares that the suspension of the spot market in New South Wales, Queensland, South Australia, Tasmania and Victoria will end at 1510 hrs on 05 September 2024.
AEMO has taken sufficient steps to exclude the original event having influence on market processes and AEMO assesses that the possibility of suspending the spot market within the next 24 hours due to the same cause is minimal. AEMO also determines that it can operate the market in accordance with the provisions of the NER.
Relevant Market Notices issued under this suspension: 118149
Manager NEM Real Time Operations
Declaration of electricity market suspension
Declaration of electricity market suspension
AEMO declares the spot market suspended in New South Wales, Queensland, South Australia, Tasmania and Victoria with Market Suspension Schedule Pricing (refer NER clause 3.14.5(b)) from Trading Interval 1355 hrs on 5 September 2024 until further notice.
Dispatch prices for the first one or two dispatch intervals of this market suspension will be reviewed manually.
Manager NEM Real Time Operations
CHG0098106 | Production | EMMS Production Bay transfer
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System
Change Title: EMMS Production Bay transfer
Change Start Date & Time: 05/09/2024 08:00:00 AEST
Change End Date & Time: 06/09/2024 17:30:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: EMMS Bay transfer is scheduled for 5th September is not expected to have any impact. If any issues are identified because of this maintenance activity, please contact the AEMO Support Hub 1300 236 600.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .
Fast Frequency Response Market - Removal of L1 FCAS dispatch cap from 9th September 2024
Following review of the operation of the Very Fast FCAS market, from 1300 hrs AEST on Monday 9th September AEMO will remove the 225 MW cap on dispatch of Very Fast Lower (L1) Contingency FCAS.
The 225 MW cap on dispatch of L1 FCAS sits well above typical disaptch volumes, and no immediate impact is expected from this change.
No other changes to the dispatch of Very Fast FCAS or FCAS constraint equation changes will be made on this date.
For information on the Fast Frequency Response (FFR) initiative please visit the website at: https://www.aemo.com.au/initiatives/major-programs/fast-frequency-response
Andrew Groom
AEMO Operations
[EventId:202409050735_confirmed] Prices for interval 05-Sep-2024 07:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0755 hrs on 5 September 2024
PRICES ARE NOW CONFIRMED for trading interval 05-Sep-2024 07:35.
In accordance with Market Notice 118132 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202409050755_confirmed] Prices for interval 05-Sep-2024 07:55 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0755 hrs on 5 September 2024
PRICES ARE NOW CONFIRMED for trading interval 05-Sep-2024 07:55.
In accordance with Market Notice 118138 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202409050750_confirmed] Prices for interval 05-Sep-2024 07:50 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0755 hrs on 5 September 2024
PRICES ARE NOW CONFIRMED for trading interval 05-Sep-2024 07:50.
In accordance with Market Notice 118136 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202409050745_confirmed] Prices for interval 05-Sep-2024 07:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0755 hrs on 5 September 2024
PRICES ARE NOW CONFIRMED for trading interval 05-Sep-2024 07:45.
In accordance with Market Notice 118134 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.