Market Notices

111951RECLASSIFY CONTINGENCY02/12/2023 09:48:55 PM

Cancellation of a Non-Credible Contingency Event: Ross - Chalumbin No.857 275 kV line and Ross - Chalumbin No.858 275 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Ross - Chalumbin No.857 275 kV and Ross - Chalumbin No.858 275 kV

Cancellation time: 02/12/2023 21:48

Constraint set(s) revoked:
Q-RSCH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 111923

Auto-generated on behalf of Manager NEM Real Time Operations
111950RECLASSIFY CONTINGENCY02/12/2023 09:48:55 PM

Cancellation of a Non-Credible Contingency Event: Collinsville North - Proserpine No.7125 132 kV line and Collinsville North - Proserpine No.7126 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Collinsville North - Proserpine No.7125 132 kV and Collinsville North - Proserpine No.7126 132 kV

Cancellation time: 02/12/2023 21:48

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 111939

Auto-generated on behalf of Manager NEM Real Time Operations
111948RECLASSIFY CONTINGENCY02/12/2023 07:33:55 PM

Cancellation of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV

Cancellation time: 02/12/2023 19:33

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 111920

Auto-generated on behalf of Manager NEM Real Time Operations
111946RECLASSIFY CONTINGENCY02/12/2023 07:08:55 PM

Cancellation of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Cancellation time: 02/12/2023 19:08

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 111916

Auto-generated on behalf of Manager NEM Real Time Operations
111945RECLASSIFY CONTINGENCY02/12/2023 06:48:55 PM

Cancellation of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV

Cancellation time: 02/12/2023 18:48

Constraint set(s) revoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1


Refer AEMO Electricity Market Notice 111942

Auto-generated on behalf of Manager NEM Real Time Operations
111944RESERVE NOTICE02/12/2023 06:31:37 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 03/12/2023

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 111941 is cancelled at 1825 hrs 02/12/2023.

Manager NEM Real Time Operations
111942RECLASSIFY CONTINGENCY02/12/2023 05:48:10 PM

Reclassification of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV

Duration: 02/12/2023 17:48 until further notice

Constraint set(s) invoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1


Auto-generated on behalf of Manager NEM Real Time Operations
111941RESERVE NOTICE02/12/2023 04:58:56 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 03/12/2023

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 111938 has been updated at 1700 hrs to the following:

[1.] From 1830 hrs 03/12/2023 to 2000 hrs 03/12/2023.
The forecast capacity reserve requirement is 1295 MW.
The minimum capacity reserve available is 1150 MW.

[2.] From 2130 hrs 03/12/2023 to 2200 hrs 03/12/2023.
The forecast capacity reserve requirement is 1306 MW.
The minimum capacity reserve available is 1278 MW.

Manager NEM Real Time Operations
111940RESERVE NOTICE02/12/2023 04:57:56 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 02/12/2023

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:


[1.] From 1900 hrs 02/12/2023 to 1930 hrs 02/12/2023.
The forecast capacity reserve requirement is 1301 MW.
The minimum capacity reserve available is 1287 MW.



Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm