Market Notices

119822MINIMUM SYSTEM LOAD03/11/2024 01:39:18 PM

Cancellation - MSL1- VIC Region 03/11/2024.

AEMO ELECTRICITY MARKET NOTICE

Cancellation - MSL1- VIC Region at 1330 hrs 03/11/2024.

Refer to Market Notice 119760 for MSL1.

Manager NEM Real Time Operations
     
119811MINIMUM SYSTEM LOAD02/11/2024 06:02:13 PM

Forecast Minimum System Load (MSL1) condition in the VIC region on 03/11/2024

AEMO ELECTRICITY MARKET NOTICE
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 03/11/2024.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1770 MW
o MSL2 - 1270 MW
o MSL3 - 770 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:

From 1100 hrs to 1400 hrs 03/11/2024. Minimum regional demand is forecast to be 1424 MW at 1300 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .

Manager NEM Real Time Operations
     
119774MINIMUM SYSTEM LOAD02/11/2024 12:11:56 PM

Cancellation - Forecast Minimum System Load MSL1 condition in the VIC Region on 02/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Forecast Minimum System Load MSL1 condition in the VIC Region at 1200 hrs 02/11/2024.

Refer to Market Notice 119742.

Manager NEM Real Time Operations
     
119760MINIMUM SYSTEM LOAD03/11/2024 11:49:58 AM

Actual Minimum System Load MSL1 condition in the VIC Region on 03/11/2024

AEMO ELECTRICITY MARKET NOTICE
Actual Minimum System Load MSL1 condition in the VIC Region on 03/11/2024

Update to Market Notice 119811 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 03/11/2024.

Minimum regional demand is forecast to be 1623 MW at 1300 hrs, and the advisory threshold is:
- MSL1 - 1770 MW
- MSL2 - 1270 MW
- MSL3 - 770 MW

The regional demand is below the MSL1 threshold. The actual MSL1 condition is forecast to exist until 1400 hrs.

Manager NEM Real Time Operations
     
119743MINIMUM SYSTEM LOAD01/11/2024 04:14:34 PM

Forecast Minimum System Load (MSL1) condition in the VIC region on 05/11/2024

AEMO ELECTRICITY MARKET NOTICE
Update to Market Notice 119682 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 05/11/2024.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1535 MW
o MSL2 - 1035 MW
o MSL3 - 535 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:

From 1000 hrs to 1430 hrs 05/11/2024. Minimum regional demand is forecast to be 1106 MW at 1300 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .

AEMO Operations
     
119742MINIMUM SYSTEM LOAD01/11/2024 04:13:32 PM

Forecast Minimum System Load (MSL1) condition in the VIC region on 02/11/2024

AEMO ELECTRICITY MARKET NOTICE
Update to Market Notice 119644 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 02/11/2024.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1685 MW
o MSL2 - 1185 MW
o MSL3 - 685 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:

From 1030 hrs to 1400 hrs 02/11/2024. Minimum regional demand is forecast to be 1304 MW at 1230 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .

AEMO Operations
     
119741MINIMUM SYSTEM LOAD01/11/2024 04:10:05 PM

Forecast Minimum System Load (MSL1) condition in the VIC region on 03/11/2024

AEMO ELECTRICITY MARKET NOTICE
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 03/11/2024.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1795 MW
o MSL2 - 1295 MW
o MSL3 - 795 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:

From 1130 hrs to 1330 hrs 03/11/2024. Minimum regional demand is forecast to be 1684 MW at 1300 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .

AEMO Operations
     
119698GENERAL NOTICE31/10/2024 12:47:07 PM

Network Augmentation Commissioned - NSW Region - 31/10/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - NSW Region - 31/10/2024

At 1200 hrs 31/10/2024, the Buronga No.4 330kV synchronous condenser has been commissioned.

Manager NEM Real Time Operations
     
119694GENERAL NOTICE31/10/2024 10:29:13 AM

Fast Frequency Response Market - Increase in R1 FCAS dispatch caps from 4th November 2024

AEMO ELECTRICITY MARKET NOTICE

Following review of the operation of the Very Fast FCAS market, from 1300 hrs AEST on Monday 4th November AEMO will increase the cap on dispatch of Very Fast Raise (R1) Contingency FCAS from 350 MW to 375 MW

No other changes to the dispatch of Very Fast FCAS or FCAS constraint equation changes will be made on this date.

For information on the Fast Frequency Response (FFR) initiative please visit the website at: https://www.aemo.com.au/initiatives/major-programs/fast-frequency-response

Andrew Groom
AEMO Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm