Filter by category
Filter by Date
Inter-regional transfer limit variation - Brinkworth- Red Hill- Bungama 132kV lines - SA region - 17/10/2024
Inter-regional transfer limit variation - Brinkworth- Red Hill- Bungama 132kV lines - SA region - 17/10/2024
At 1846 hrs 17/10/2024 there was an unplanned outage of Brinkworth- Red Hill- Bungama 132kV lines.
The following constraint set(s) invoked at 1855 hrs 17/10/2024
S-BRBG
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Hummocks - Bungama 132kV line - SA region - 17/10/2024
Inter-regional transfer limit variation - Hummocks - Bungama 132kV line - SA region - 17/10/2024
At 1842 hrs 17/10/2024 there was an unplanned outage of Hummocks - Bungama 132kV line.
The following constraint set(s) invoked at 1850 hrs 17/10/2024
S-HUBG
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Blyth West - Munno Para 275kV line- SA region - 17/10/2024
Inter-regional transfer limit variation - Blyth West - Munno Para 275kV line - SA region - 17/10/2024
At 1848 hrs 17/10/2024 there was an unplanned outage of Blyth West - Munno Para 275kV line.
The following constraint set(s) invoked at 1855 hrs 17/10/2024
S-BWMP
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the QLD region - 17/10/2024
Cancellation of Actual (LOR1) condition in the QLD region - 17/10/2024
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.118993 is cancelled at 1839 hrs 17/10/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 17/10/2024
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 17/10/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs
The capacity reserve requirement is 1136 MW
The minimum capacity reserve available is 1076 MW
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Moorabool to Sydenham 500 kV No.2 line - VIC region - 09/10/2024
Inter-regional transfer limit variation - Moorabool to Sydenham 500 kV No.2 line - VIC region - 09/10/2024
A planned outage of Moorabool to Sydenham 500 kV No.2 line in the VIC region was scheduled from 0600 hrs 01/10/2024 to 2030 hrs 11/10/2024.
The outage has been completed and Moorabool to Sydenham 500 kV No.2 line returned to service at 1940 hrs 09/10/2024
Constraint set(s) revoked: V-MLSY_NOEMTT_R
Manager NEM Real Time Operations
Managing outages that create a credible risk of SA islanding
From 9th Oct 2024 AEMO will change constraints used during outages that create a credible risk of SA islanding.
From this date AEMO will:
1) Increase the maximum allowable flow on the V-SA interconnector from 50 MW to 250 MW in the VIC to SA direction, where the transmission outages is a planned outage.
2) Operate the SA region to the default 49-51 Hz target frequency containment band following a contingency event resulting in actual SA islanding. In order to meet this requirement, AEMO may now procure Contingency Raise FCAS locally from the SA region during these outages.
These changes reflect updated advice received by AEMO from the SA Jurisdictional System Security Coordinator.
The first network outage affected by this change is planned for 14th October 2024.
Andrew Groom
AEMO Operations
Inter-regional transfer limit variation - Bannaby -Sydney West 39 330 kV line - NSW region - 03/10/2024
Inter-regional transfer limit variation - Bannaby -Sydney West 39 330 kV line- NSW region - 03/10/2024
A planned outage of Bannaby -Sydney West 39 330 kV line in the NSW region was scheduled from 0700 hrs 16/09/2024 to 1600 hrs 11/10/2024.
The outage has been completed and Bannaby -Sydney West 39 330 kV line returned to service at 0920 hrs 03/10/2024
Constraint set revoked: N-BYSW_39_15M
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Stockdill - Upper Tumut 1 330 kV line- NSW region - 29/09/2024
Inter-regional transfer limit variation - Stockdill - Upper Tumut 1 330 kV line - NSW region - 29/09/2024
At 0313 hrs 29/09/2024 there was an unplanned outage of Stockdill - Upper Tumut 1 330 kV line.
The following constraint set invoked at 0320 hrs 29/09/2024
N-SDUT_1
This constraint set contains equations with the following interconnectors on the LHS.
V-S-MNSP1
VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations