Filter by category
Filter by Date
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 1100 hrs 30/11/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 29/11/2024
Cancellation of Actual (LOR1) condition in the NSW region - 29/11/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121262 is cancelled at 1815 hrs 29/11/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 29/11/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 29/11/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs
The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 1301 MW
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 29/11/2024
Cancellation of Actual (LOR1) condition in the NSW region - 29/11/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121260 is cancelled at 1717 hrs 29/11/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 29/11/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 29/11/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1730 hrs
The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 1183 MW
Manager NEM Real Time Operations
[EventId:202411291530_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 29 November 2024 15:30
Issued by Australian Energy Market Operator Ltd at 1530 hrs on 29 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 November 2024.
Refer to market notice: 121235
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1530 hrs on 29 November 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202411291300_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 29 November 2024 13:00
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 29 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1300 hrs on 29 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202411291230_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 29 November 2024 12:30
Issued by Australian Energy Market Operator Ltd at 1230 hrs on 29 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 November 2024.
Refer to market notice: 121233
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1230 hrs on 29 November 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202411291035_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 29 November 2024 10:35
Issued by Australian Energy Market Operator Ltd at 1035 hrs on 29 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1035 hrs on 29 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.