121008POWER SYSTEM EVENTS26/11/2024 04:55:00 PM

Non-credible contingency event - NSW region - 26/11/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - NSW region - 26/11/2024

At 1637 hrs Uranquinty Unit 12 tripped and at 1639 hrs Uranquinty Units 11 and 13 tripped.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
     
120943MARKET SYSTEMS25/11/2024 05:22:50 PM

INC0138597 - RESOLVED - EMMS

AEMO ELECTRICITY MARKET NOTICE

SERVICE INTERRUPTION - SERVICE RESTORED

The Electricity Market Management System service has been restored.

For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
     
120926MARKET SYSTEMS25/11/2024 03:12:58 PM

INC0138597 - ALERT - EMMS

SERVICE INTERRUPTION - ALERT
AEMO is experiencing a service interruption relating to the Electricity Market Management System service.

AEMO is working on the issue and will provide updates as more information becomes available.

For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
     
120919INTER-REGIONAL TRANSFER25/11/2024 02:03:31 PM

Inter-Regional Transfer limit variation - Murraylink

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Murraylink

There has been an unplanned outage of Murraylink.

The following constraint set was invoked at 1405 hrs 25/11/2024

I-ML_ZERO

The constraint set contains the following interconnector on the left hand side.

V-S-MNSP1

Refer to AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
     
120890RESERVE NOTICE24/11/2024 06:45:54 PM

Cancellation of Actual (LOR1) condition in the NSW region - 24/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 24/11/2024

The Actual LOR1 Condition in the NSW region advised in AEMO Electricity Market Notice No.120889 is cancelled at 1845 hrs 24/11/2024.

Manager NEM Real Time Operations
     
120889RESERVE NOTICE24/11/2024 06:17:52 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 24/11/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 24/11/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs

The capacity reserve requirement is 1541 MW
The minimum capacity reserve available is 1460 MW

Manager NEM Real Time Operations
     
120836INTER-REGIONAL TRANSFER22/11/2024 07:32:00 PM

Inter-regional transfer limit variation - Directlink - NSW region - 22/11/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Directlink - NSW region - 22/11/2024

At 1911 hrs 22/11/2024 there was an unplanned outage of the No.2 leg of Directlink.

The following constraint set(s) invoked at 1920 hrs 22/11/2024
N-X_MBTE_2

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
120835RESERVE NOTICE22/11/2024 06:41:52 PM

Cancellation of Actual (LOR1) condition in the NSW region - 22/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 22/11/2024

The Actual LOR1 Condition in the NSW region advised in AEMO Electricity Market Notice No.120833 is cancelled at 1838 hrs 22/11/2024.

Manager NEM Real Time Operations
     
120833RESERVE NOTICE22/11/2024 06:12:08 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW Region on 22/11/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 22/11/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.

The Actual LOR1 condition is forecast to exist until 1830 hrs.

The forecast capacity reserve requirement is 1396 MW.
The minimum capacity reserve available is 1348 MW.


Manager NEM Real Time Operations
     