STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 27/11/2024
AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1800 hrs 27/11/2024 to 1830 hrs 27/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 84 MW at 1800 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/11/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120819 has been updated at 1500 hrs 22/11/2024 to the following:
From 1700 hrs to 1900 hrs 27/11/2024.
The forecast capacity reserve requirement is 525 MW.
The minimum capacity reserve available is 110 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 27/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120818 has been updated at 1500 hrs 22/11/2024 to the following:
From 1330 hrs to 2000 hrs 27/11/2024.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 64 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 27/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120756 has been updated at 1400 hrs 22/11/2024 to the following:
1. From 1700 hrs to 1800 hrs 27/11/2024.
The forecast capacity reserve requirement is 1005 MW.
The minimum capacity reserve available is 613 MW.
2. From 1830 hrs to 2000 hrs 27/11/2024.
The forecast capacity reserve requirement is 1005 MW.
The minimum capacity reserve available is 525 MW.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 25/11/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 120755 is cancelled at 1400 hrs 22/11/2024.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 26/11/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 120757 is cancelled at 1400 hrs 22/11/2024.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 27/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120754 has been updated at 1400 hrs 22/11/2024 to the following:
1. From 1100 hrs to 1400 hrs 27/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.
2. From 1500 hrs to 1600 hrs 27/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.
3. From 1930 hrs to 2030 hrs 27/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 706 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120753 has been updated at 1400 hrs 22/11/2024 to the following:
From 1300 hrs to 2359 hrs 26/11/2024.
The forecast capacity reserve requirement is 1555 MW.
The minimum capacity reserve available is 825 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 25/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120751 has been updated at 1400 hrs 22/11/2024 to the following:
From 1600 hrs to 2100 hrs 25/11/2024.
The forecast capacity reserve requirement is 1558 MW.
The minimum capacity reserve available is 828 MW.