116550ADMINISTERED PRICE CAP08/05/2024 07:45:12 PM

[EventId:197] AP STARTED for ENERGY in NSW1 at 08 May 2024 19:45

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1945 hrs on 08 May 2024

ADMINISTERED PRICE PERIOD DECLARED in NSW1 region.

AEMO has determined that the rolling sum of the uncapped spot prices for the NSW1 region over the previous 2016 trading intervals has exceeded the cumulative price threshold (CPT) of $1,490,200.00.

In accordance with Clause 3.14.2(b) of the National Electricity Rules, AEMO has determined that an administered price period will commence at the trading interval starting 1955 hrs on 08 May 2024 and will continue through to the end of that trading day.

An administered price cap (APC) of 600 $/MWh will apply to all trading intervals during this administered price period. This APC will apply to spot prices and to all market ancillary service prices in the NSW1 region.

An administered floor price (AFP) of -600 $/MWh will apply to spot prices.

AEMO will continue to monitor the rolling sum of the uncapped spot prices and issue further Market Notices as required.

This is an AEMO autogenerated Market Notice.
114889CONSTRAINTS20/02/2024 07:23:40 AM

Update to system strength constraints in North Queensland

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 110677

AEMO and Powerlink are continuing to investigate system strength requirements in North Queensland.
Due to commissioning of new feeder 8905 (H13 Ross - H39 Woree) 275kV line in Far North Queensland, the system normal system strength equations for low North Queensland demands and all Karreya stations out of service conditions have been revised.

A revision to the constraint equations will be implemented at 1400 hrs on Tuesday 20th February 2024.

The new system strength combinations have now published in a limits advice document on AEMO's website. For more information refer to the new limits advice: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice

This advice contains all the combinations for Queensland for system normal cases.

Below constraint equations in the Q-NIL set will be modified:

- Q_NIL_STRGTH_KBWF
- Q_NIL_STRGTH_KBWF_I
- Q_NIL_STRGTH_HAUSF
- Q_NIL_STRGTH_HAUSF_I
- Q_NIL_STRGTH_MEWF
- Q_NIL_STRGTH_MEWF_I

AEMO Operations
114644RESERVE NOTICE13/02/2024 04:15:16 PM

Cancellation of Actual (LOR2) condition in the VIC region - 13/02/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR2) condition in the VIC region - 13/02/2024

The Actual LOR2 Condition in the VIC Region advised in AEMO Electricity Market Notice No.114589 is cancelled at 1614 hrs 13/02/2024.

Manager NEM Real Time Operations
114607LOAD SHED13/02/2024 02:35:06 PM

Load Shedding Direction in the Vic Region

AEMO ELECTRICITY MARKET NOTICE

Load Shedding Direction in the Vic Region

AEMO has directed load shedding commencing at 1420 hrs 13/02/2024
in the Victoria region to restore power system security.

The direction was issued under section 116 of the NEL, and was a clause 4.8.9 instruction under the NER.

Manager NEM Real Time Operations
112364RESERVE NOTICE14/12/2023 06:16:35 PM

Cancellation of Actual (LOR2) condition in the NSW region - 14/12/2023

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR2) condition in the NSW region - 14/12/2023

The Actual LOR2 Condition in the NSW Region advised in AEMO Electricity Market Notice No.112362 is cancelled at 1810 hrs 14/12/2023.

Manager NEM Real Time Operations
112362RESERVE NOTICE14/12/2023 06:00:52 PM

Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 14/12/2023

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 14/12/2023

An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR2 condition is not forecast in Pre Dispatch

The capacity reserve required is 690 MW
The minimum reserve available is 678 MW

AEMO is seeking an immediate market response.

An insufficient market response may require AEMO to implement a AEMO intervention event.