Market Notices

120745MARKET INTERVENTION21/11/2024 01:35:59 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 120723

Direction is cancelled from: 1330 hrs 21/11/2024

Manager NEM Real Time Operations
     
120744MARKET INTERVENTION21/11/2024 01:30:24 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 120722

Direction is cancelled from: 1330 hrs 21/11/2024

Manager NEM Real Time Operations
     
120737NON-CONFORMANCE21/11/2024 02:10:16 AM

NON-CONFORMANCE Region NSW1 Thursday, 21 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 21 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP5
Duration: 21/11/2024 01:55 to 21/11/2024 02:10
Amount: -20 MW
Constraint: NC-N_VP5

Auto-generated on behalf of Manager NEM Real Time Operations
     
120723MARKET INTERVENTION20/11/2024 04:29:17 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 120680

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1500 hrs 21/11/2024.

The direction update is issued at 1630 hrs 20/11/2024.

Manager NEM Real Time Operations
     
120722MARKET INTERVENTION20/11/2024 04:28:21 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 120679

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1330 hrs 21/11/2024.

The direction update is issued at 1630 hrs 20/11/2024.

Manager NEM Real Time Operations
     
120721NON-CONFORMANCE20/11/2024 03:35:26 PM

NON-CONFORMANCE Region QLD1 Wednesday, 20 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 20 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 20/11/2024 06:35 to 20/11/2024 15:35
Amount: -45 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
120720RESERVE NOTICE20/11/2024 03:23:53 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 24/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120673 is cancelled at 1400 hrs 20/11/2024

AEMO Operations
     
120719RESERVE NOTICE20/11/2024 03:22:54 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

1. From 0530 hrs to 0800 hrs 27/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1164 MW.

2. From 0830 hrs to 2300 hrs 27/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.

AEMO Operations
     
120718RESERVE NOTICE20/11/2024 03:21:44 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120674 has been updated at 1400 hrs 20/11/2024 to the following:

1. From 1130 hrs to 1400 hrs 26/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 889 MW.

2. From 2030 hrs to 2300 hrs 26/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.

AEMO Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm