Filter by category
Filter by Date
Update - Pre dispatch demand forecast - Qld region
Update - Pre dispatch demand forecast - Qld region
Refer market notice: 119666
The issue relating to the Queensland Pre dispatch demand forecast has been resolved.
Manager NEM Real Time Operations
Pre dispatch demand forecast - Qld region
Pre dispatch demand forecast - Qld region
AEMO is aware of an error in the Queensland pre dispatch demand forecast.
AEMO is currently working to resolve the issue.
Dispatch results are not impacted.
Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Monday, 28 October 2024
NON-CONFORMANCE SA1 Region Monday, 28 October 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: TB2BG1, TB2BL1
Aggregate Dispatch Group: TB2HYB_ADG1
Duration: 28/10/2024 12:05 to 28/10/2024 12:55
Amount: 39 MW
Constraint: NC-S_TB2HYB_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Sunday, 27 October 2024
NON-CONFORMANCE NSW1 Region Sunday, 27 October 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BW04
Duration: 27/10/2024 15:35 to 27/10/2024 15:40
Amount: -78 MW
Constraint: NC-N_BW04
Auto-generated on behalf of Manager NEM Real Time Operations
CHG0098814 | Completed | Production | MSATS and eMDM November Maintenance Release
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: MSATS and eMDM November Maintenance Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
NON-CONFORMANCE Region VIC1 Saturday, 26 October 2024
NON-CONFORMANCE VIC1 Region Saturday, 26 October 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GANNB1
Duration: 26/10/2024 19:15 to 26/10/2024 19:25
Amount: -25 MW
Constraint: NC-V_GANNB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Friday, 25 October 2024
NON-CONFORMANCE NSW1 Region Friday, 25 October 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 25/10/2024 08:30 to 25/10/2024 09:15
Amount: -9 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
CHG0099241 | Completed | Production | Migrate DEV / TEST / Pre-Production (PPD) VLAN 104 Gateway in Norwest from the Old Core Switches to the New Core Switches.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Local Area Network
Change Title: Migrate DEV / TEST / Pre-Production (PPD) VLAN 104 Gateway in Norwest from the Old Core Switches to the New Core Switches.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0099235 | Completed | Production | Migrate Pre-Production (PPD) VLAN 108 Gateway in Norwest from the Old Core Switches to the New Core Switches.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Local Area Network
Change Title: Migrate Pre-Production (PPD) VLAN 108 Gateway in Norwest from the Old Core Switches to the New Core Switches.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.