120306POWER SYSTEM EVENTS12/11/2024 11:43:52 AM

Update - Non-credible contingency event - VIC region - 12/11/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - VIC region - 12/11/2024

Refer AEMO Electricity Market Notice 120305

At 1135 hrs the Yallourn No 1 220 kV bus was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     
120305POWER SYSTEM EVENTS12/11/2024 10:55:18 AM

Non-credible contingency event - VIC region - 12/11/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - VIC region - 12/11/2024

At 1041 hrs the Yallourn No 1 220 kV bus and Yallourn Unit 4 tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.


The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
120197NON-CONFORMANCE09/11/2024 09:10:15 PM

NON-CONFORMANCE Region VIC1 Saturday, 9 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Saturday, 9 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: GANNB1
Duration: 09/11/2024 20:55 to 09/11/2024 21:10
Amount: 9 MW
Constraint: NC-V_GANNB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
120179NON-CONFORMANCE09/11/2024 02:45:22 AM

NON-CONFORMANCE Region NSW1 Saturday, 9 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 9 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP5
Duration: 09/11/2024 02:40 to 09/11/2024 02:45
Amount: -42 MW
Constraint: NC-N_VP5

Auto-generated on behalf of Manager NEM Real Time Operations
     
120142NON-CONFORMANCE08/11/2024 12:45:20 PM

NON-CONFORMANCE Region NSW1 Friday, 8 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Friday, 8 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 08/11/2024 12:30 to 08/11/2024 12:45
Amount: 16 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
120137NON-CONFORMANCE08/11/2024 10:10:24 AM

NON-CONFORMANCE Region NSW1 Friday, 8 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Friday, 8 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BHB1
Duration: 08/11/2024 09:15 to 08/11/2024 10:10
Amount: 25 MW
Constraint: NC-N_BHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
120117RESERVE NOTICE07/11/2024 08:13:20 PM

Cancellation of Actual (LOR1) condition in the QLD region - 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 07/11/2024

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.120112 is cancelled at 2010 hrs 07/11/2024.

Manager NEM Real Time Operations
     
120115RESERVE NOTICE07/11/2024 07:50:30 PM

Cancellation of Actual (LOR1) condition in the NSW region - 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 07/11/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.120113 is cancelled at 1945 hrs 07/11/2024.

Manager NEM Real Time Operations
     
120113RESERVE NOTICE07/11/2024 05:47:43 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 07/11/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs

The capacity reserve requirement is 1430 MW
The minimum capacity reserve available is 1201 MW

Manager NEM Real Time Operations
     