Update to system normal constraint equation in NSW for transient voltage stability in south-west NSW
Refer to market notice 92840.
Transgrid has advised AEMO of an update to the transient voltage stability limit in south-west NSW for loss of Darlington Point to Wagga (63) 330 kV line. The limit will include terms for the Darlington Point and Riverina BESS.
The following constraint equation will be updated with the above changes at 1100 hrs Friday 20th September 2024.
N::N_NIL_63
For full details on the formulation, the new constraint equation has now been loaded into AEMO's pre-production systems.
For further details on these constraint equation please contact ben.blake@aemo.com.au
Ben Blake
AEMO Operations
Update - Non-credible contingency event - TAS region - 19/09/2024
Update - Non-credible contingency event - TAS region - 19/09/2024
Refer AEMO Electricity Market Notice 118321
At 1446 hrs the Gordon - Chapel St No 1 and No 2 220 kV lines were returned to service.
This non-credible contingency event was caused by lightning. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Manager NEM Real Time Operations
Update - Non-credible contingency event - TAS region - 19/09/2024
Update - Non-credible contingency event - TAS region - 19/09/2024
At 1340 hrs the Gordon - Chapel St No1 and No 2 220 kV lines tripped.
AEMO did not instruct load shedding.
AEMO has advised of approximately 112 MW disconnection of bulk electrical load,
disconnection of generation at Studland Bay Wind generator (71 MW) and 23 MW generation reduction at Gordon Power station.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Non-credible contingency event - TAS region - 19/09/2024
Non-credible contingency event - TAS region - 19/09/2024
At 1340 hrs the Gordon - Chapel St No1 and No 2 220 kV lines tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Update - Non-credible contingency event - VIC region - 06/09/2024
Update - Non-credible contingency event - VIC region - 06/09/2024
Refer AEMO Electricity Market Notice 118166
At 2005 hrs the Loy Yang PS No. 4 500 kV bus was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - VIC region - 06/09/2024
Non-credible contingency event - VIC region - 06/09/2024
At 1222 hrs the Loy Yang PS No. 4 500 kV bus tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Update - Non-credible contingency event - VIC region - 28/08/2024
Update - Non-credible contingency event - VIC region - 28/08/2024
Refer AEMO Electricity Market Notice 117908
At 0134 hrs the APD No 2 Potline was returned to service.
At 0200 hrs the APD No 1 Potline was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - VIC region - 28/08/2024
Non-credible contingency event - VIC region - 28/08/2024
At 0001 hrs the APD No1 Potline and the APD No 2 Potline tripped.
AEMO did not instruct load shedding.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Update - Non-credible contingency event - TAS region - 25/08/2024
Update - Non-credible contingency event - TAS region - 25/08/2024
Refer AEMO Electricity Market Notice 117782
At 1023 hrs the New Norfolk A 110kV Bus was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations