Cancellation of Reclassification of a Non-Credible Contingency Event: Tully - Cardwell No.7389 132 kV Line and Ross - Woree No. 8905 275 kV Line
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Tully - Cardwell No.7389 132 kV Line and Ross - Woree No. 8905 275 kV Line
Cancellation time: 05/03/2024 19:15
Constraint set(s) revoked: Nil
Refer AEMO Electricity Market Notice 115498
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Collinsville - Stoney Creek 7306 132KV LINE line and Collinsville - Newlands 7121 132KV LINE line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Collinsville - Stoney Creek 7306 132KV LINE and Collinsville - Newlands 7121 132KV LINE
Duration: 05/03/2024 16:42 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Collinsville North - Proserpine No.7125 132 kV line and Collinsville North - Proserpine No.7126 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Collinsville North - Proserpine No.7125 132 kV and Collinsville North - Proserpine No.7126 132 kV
Duration: 05/03/2024 16:42 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Strathmore - Clare South No.7208 132 kV line and Strathmore - Clare South tee King Creek No.7128 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Strathmore - Clare South No.7208 132 kV and Strathmore - Clare South tee King Creek No.7128 132 kV
Duration: 05/03/2024 15:50 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 04/03/2024
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 04/03/2024
Refer Market Notice 115482
The AEMO Intervention Event and all associated directions are cancelled from 1400 hrs 05/03/2024
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Tully - Cardwell No.7389 132 kV line and Ross - Woree No. 8905 275 kV line
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly, AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Tully - Cardwell No.7389 132 kV line and Ross - Woree No. 8905 275 kV line
Duration: 05/03/2024 13:25 until further notice
Constraint set(s) invoked: NONE
Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Middle Ridge No.2 275/110 kV Transformer line and Middle Ridge No.3 275/110 kV Transformer line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Middle Ridge No.2 275/110 kV Transformer and Middle Ridge No.3 275/110 kV Transformer
Cancellation time: 04/03/2024 20:24
Constraint set(s) revoked:
Q-MR_TX2_3_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Refer AEMO Electricity Market Notice 115477
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Strathmore - Clare South No.7208 132 kV line and Strathmore - Clare South tee King Creek No.7128 132 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Strathmore - Clare South No.7208 132 kV and Strathmore - Clare South tee King Creek No.7128 132 kV
Cancellation time: 04/03/2024 19:19
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 115488
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV
Cancellation time: 04/03/2024 19:14
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 115486
Auto-generated on behalf of Manager NEM Real Time Operations