NON-CONFORMANCE Region VIC1 Saturday, 10 February 2024
NON-CONFORMANCE VIC1 Region Saturday, 10 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GANNSF1
Duration: 10/02/2024 10:40 to 10/02/2024 10:55
Amount: 25 MW
Constraint: NC-V_GANNSF1
Auto-generated on behalf of Manager NEM Real Time Operations
NEM Local Temperature Alerts for SA, VIC from 09 Feb 2024 to 13 Feb 2024
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Port Augusta Ap (39+ Deg C): 11th Feb, 12th Feb
VIC
Mildura Ap (39+ Deg C): 12th Feb, 13th Feb
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
NEM Local Temperature Alerts for SA from 08 Feb 2024 to 12 Feb 2024
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Port Augusta Ap (39+ Deg C): 11th Feb, 12th Feb
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
NON-CONFORMANCE Region QLD1 Wednesday, 7 February 2024
NON-CONFORMANCE QLD1 Region Wednesday, 7 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 07/02/2024 15:40 to 07/02/2024 15:50
Amount: -37 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Wednesday, 7 February 2024
NON-CONFORMANCE VIC1 Region Wednesday, 7 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GLRWNSF1
Duration: 07/02/2024 14:00 to 07/02/2024 14:05
Amount: 103 MW
Constraint: NC-V_GLRWNSF1
Auto-generated on behalf of Manager NEM Real Time Operations
QNI Minor testing (NSW to Qld) 7th February 2024
Refer to market notice 113265
There is an opportunity for testing QNI Minor for flows from NSW to Qld up to 750 MW on Wednesday 7th February 2024 from 1400 to 1800hrs.
This test includes a trip and reclose of a line in northern NSW.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade
Ben Blake
AEMO Operations
Fast Frequency Response Market - Increase in L1 FCAS dispatch cap from 12 February 2024.
Following review of the operation of the Very Fast FCAS market, from 1300 hrs AEST on Monday 12 Febraury AEMO will:
Increase the cap on dispatch of Very Fast Lower (L1) Contingency FCAS from 100 MW to 125 MW
Retain the cap on dispatch of Very Fast Raise (R1) Contingency FCAS at 225 MW
No other changes to the dispatch of Very Fast FCAS or FCAS constraint equation changes will be made on this date.
For information on the Fast Frequency Response (FFR) initiative please visit the website at: https://www.aemo.com.au/initiatives/major-programs/fast-frequency-response
Andrew Groom
AEMO Operations
NON-CONFORMANCE Region NSW1 Monday, 5 February 2024
NON-CONFORMANCE NSW1 Region Monday, 5 February 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: RIVNBG2, RIVNBL2
Aggregate Dispatch Group: RESS2_ADG1
Duration: 05/02/2024 12:15 to 05/02/2024 12:25
Amount: 49 MW
Constraint: NC-N_RESS2_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Monday, 5 February 2024
NON-CONFORMANCE NSW1 Region Sunday, 4 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: SEBSF1
Duration: 04/02/2024 12:45 to 05/02/2024 09:40
Amount: 35 MW
Constraint: NC-N_SEBSF1
Auto-generated on behalf of Manager NEM Real Time Operations