112229PRICES UNCHANGED13/12/2023 10:31:34 AM

[EventId:202312131015_confirmed] Prices for interval 13-Dec-2023 10:15 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1030 hrs on 13 December 2023

PRICES ARE NOW CONFIRMED for trading interval 13-Dec-2023 10:15.

In accordance with Market Notice 112224 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
112228PRICES UNCHANGED13/12/2023 10:30:13 AM

[EventId:202312131010_confirmed] Prices for interval 13-Dec-2023 10:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1030 hrs on 13 December 2023

PRICES ARE NOW CONFIRMED for trading interval 13-Dec-2023 10:10.

In accordance with Market Notice 112222 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
112218MARKET INTERVENTION13/12/2023 06:48:53 AM

Possible intervention to manage power system security in SA Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA Region

The synchronous generating units currently expected to be synchronised in SA from 0130 hrs 14/12/2023 will be inadequate to maintain a secure operating state in SA.

AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
112212MARKET INTERVENTION12/12/2023 05:01:31 PM

Direction - SA region 12/12/2023

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 12/12/2023

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1705 hrs on 12/12/2023.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
112209RESERVE NOTICE12/12/2023 03:04:17 PM

STPASA - Update to the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 14/12/2023

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 112182 has been updated at 1400 hrs 12/12/2023 to the following:

From 1730 hrs to 1800 hrs 14/12/2023.
The forecast capacity reserve requirement is 1285 MW.
The minimum capacity reserve available is 1193 MW.


AEMO Operations
112208RESERVE NOTICE12/12/2023 03:05:35 PM

STPASA - Update to the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/12/2023

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 112183 has been updated at 1400 hrs 12/12/2023 to the following:

From 2000 hrs to 2030 hrs 14/12/2023.
The forecast capacity reserve requirement is 1735 MW.
The minimum capacity reserve available is 1569 MW.


AEMO Operations
112206MARKET INTERVENTION12/12/2023 02:23:46 PM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA region

Refer AEMO Electricity Market Notice 112204

The synchronous generating units currently expected to be synchronised in SA from 0730 hrs 13/12/2023 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1700 hrs 12/12/2023, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
112204MARKET INTERVENTION12/12/2023 12:54:12 PM

Possible intervention to manage power system security in SA Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA Region

The synchronous generating units currently expected to be synchronised in SA from 0730 hrs 13/12/2023 will be inadequate to maintain a secure operating state in SA.

AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
112185MARKET INTERVENTION11/12/2023 03:20:21 PM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA region

Refer AEMO Electricity Market Notice 112176

The synchronous generating units currently expected to be synchronised in SA from 0900 hrs 12/12/2023 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 0800 hrs 12/12/2023, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations