Network Augmentation Commissioned - SA Region - 12/12/2023
Network Augmentation Commissioned - SA Region - 12/12/2023
Commissioned: Robertstown - Bundey No. 2 275 kV Line
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Blyth West- Munno Para 275 kV Line - SA region - 11/12/2023
Inter-regional transfer limit variation - Blyth West- Munno Para 275 kV Line - SA region - 11/12/2023
At 1446 hrs 11/12/2023 there was an unplanned outage of Blyth West- Munno Para 275 kV Line.
However, due to the concurrent Non-credible contingency event - SA region - 11/12/2023, refer AEMO Electricity Market Notice 112187, additional inter-regional constraints were not required until the remaining Mintaro - Waterloo 132 kV Line was returned to service.
The following constraint set(s) invoked at 1610 hrs 11/12/2023
S-BWMP
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
NEM Local Temperature Alerts for VIC from 11 Dec 2023 to 15 Dec 2023
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
VIC
Mildura Ap (39+ Deg C): 12th Dec
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Network Augmentation Commissioned - SA Region - 10/12/2023
Network Augmentation Commissioned - SA Region - 10/12/2023
Commissioned: Robertstown - Bundey No. 1 275 kV Line
Bundey 275 kV Swtichyard
Manager NEM Real Time Operations
Network Augmentation Commissioned - NSW Region - 08/12/2023
Network Augmentation Commissioned - NSW Region - 08/12/2023
Commissioned: Wellington - Wellington North Solar Farm 7H 330 kV Line
Manager NEM Real Time Operations
NEM Local Temperature Alerts for NSW, SA, VIC from 08 Dec 2023 to 12 Dec 2023
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
NSW
Yass (39+ Deg C): 9th Dec
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Cancellation Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)
Cancellation Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)
Refer AEMO Electricity Market Notice 112048
AEMO has been notified that the controls to vary Murraylink output are now available.
Constraint set I-CTRL_ISSUE_ML revoked at 0115 hrs.
Manager NEM Real Time Operations
Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)
Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region).
Refer AEMO Electricity Market Notice 112047
AEMO has been notified that the controls to vary Directlink output are now available.
Constraint set I-CTRL_ISSUE_TE revoked at 0115 hrs.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)
Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)
AEMO has been notified that the controls to vary Murraylink output are unavailable until further notice.
Constraint set I-CTRL_ISSUE_ML invoked from 0025 hrs.
The constraint set contains equations with the following interconnector on the LHS:
V-S-MNSP1
Manager NEM Real Time Operations