Filter by category
Filter by Date
[EventId:202405071930_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 07 May 2024 19:30
Issued by Australian Energy Market Operator Ltd at 1930 hrs on 7 May 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 7 May 2024.
Refer to market notice: 116512
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1930 hrs on 7 May 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202405071715_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 07 May 2024 17:15
Issued by Australian Energy Market Operator Ltd at 1715 hrs on 7 May 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 7 May 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1715 hrs on 7 May 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202405051830_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 05 May 2024 18:30
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 5 May 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 5 May 2024.
Refer to market notice: 116486
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1830 hrs on 5 May 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202405051730_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 05 May 2024 17:30
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 5 May 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 5 May 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1730 hrs on 5 May 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202405031900_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 03 May 2024 19:00
Issued by Australian Energy Market Operator Ltd at 1900 hrs on 3 May 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 May 2024.
Refer to market notice: 116458
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1900 hrs on 3 May 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202405031630_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 03 May 2024 16:30
Issued by Australian Energy Market Operator Ltd at 1630 hrs on 3 May 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 May 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1630 hrs on 3 May 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202405021900_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 02 May 2024 19:00
Issued by Australian Energy Market Operator Ltd at 1900 hrs on 2 May 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 2 May 2024.
Refer to market notice: 116442
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1900 hrs on 2 May 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202405021730_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 02 May 2024 17:30
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 2 May 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 2 May 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1730 hrs on 2 May 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202404301730_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 30 April 2024 17:30
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 30 April 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 April 2024.
Refer to market notice: 116390
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1730 hrs on 30 April 2024.
This is an AEMO autogenerated Market Notice.