117908POWER SYSTEM EVENTS28/08/2024 01:02:22 AM

Non-credible contingency event - VIC region - 28/08/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - VIC region - 28/08/2024

At 0001 hrs the APD No1 Potline and the APD No 2 Potline tripped.

AEMO did not instruct load shedding.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
117783POWER SYSTEM EVENTS25/08/2024 10:33:54 AM

Update - Non-credible contingency event - TAS region - 25/08/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - TAS region - 25/08/2024

Refer AEMO Electricity Market Notice 117782

At 1023 hrs the New Norfolk A 110kV Bus was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
117782POWER SYSTEM EVENTS25/08/2024 09:24:53 AM

Non-credible contingency event - TAS region - 25/08/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - TAS region - 25/08/2024

At 0850 hrs the New Norfolk A 110kV Bus tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
117562RESERVE NOTICE05/08/2024 07:17:58 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 05/08/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 117561 is cancelled at 1915 hrs 05/08/2024.

Manager NEM Real Time Operations
117561RESERVE NOTICE05/08/2024 06:21:59 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 05/08/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 117548 has been updated at 1815 hrs to the following:

[1.] From 1930 hrs 05/08/2024 to 2130 hrs 05/08/2024.
The forecast capacity reserve requirement is 450 MW.
The minimum capacity reserve available is 386 MW.

Manager NEM Real Time Operations
117547RESERVE NOTICE05/08/2024 04:27:39 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 05/08/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:

[1.] From 1900 hrs 05/08/2024 to 2200 hrs 05/08/2024.
The forecast capacity reserve requirement is 450 MW.
The minimum capacity reserve available is 317 MW.

Manager NEM Real Time Operations
117503POWER SYSTEM EVENTS30/07/2024 07:07:11 AM

Non-credible contingency event - QLD region - 30/07/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 30/07/2024

At 0537 hrs the Darling Downs Power Station GT1, GT3 and and the steam turbine tripped from 484 MW.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
117501RESERVE NOTICE29/07/2024 05:49:35 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region [beginning] on 29/07/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 117497 is cancelled at 0545 hrs 29/07/2024.

Manager NEM Real Time Operations
117500POWER SYSTEM EVENTS28/07/2024 05:14:14 PM

Update - Non-credible contingency event - QLD region - 27/07/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - QLD region - 27/07/2024

Refer AEMO Electricity Market Notice 117487

At 1702 hrs the H38 Goodna No. 2 275kV Bus and the H38 Goodna No. 1 275/132kV transformer was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations